21
Banco Construction
NAN%
# | District Name | Package Name | Physical Progress | Scheme Name | Physical Progress | Revised DPR Status | Intake NOC Status | Pert Chart Status | Vetting Status | Distribution System (KM) | Overhead Tank | CWR | Intake Well | Treatment Plant | Raw Water Pumping Plant | Clear Water Pumping Plant | Staff Quarter | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
R | S | R | S | R | S | R | S | R | S | R | S | R | S | R | S | ||||||||||
1 | Lalitpur | Tori | 75.49% | Tori GOV Water Supply Scheme | 75.49% | Approved | NOC Recieved | View File | Vetted by IIT | View File | 46.1 | 45.5 | 8 | 8 | 2 | 2 | 1 | 1 | 1 | 1 | 1 | 1 | 2 | 2 | 3 | 2 |
Lalitpur Total | 75.49% | 75.49% | 46.1 | 45.5 | 8 | 8 | 2 | 2 | 1 | 1 | 1 | 1 | 1 | 1 | 2 | 2 | 3 | 2 | |||||||
Grand Total | 46.1 | 45.5 | 8 | 8 | 2 | 2 | 1 | 1 | 1 | 1 | 1 | 1 | 2 | 2 | 3 | 2 |