Megha
  Contractor:   

Megha


  No. of Packages:   


  No. of Schemes:   


  Physical Achievement:   

NAN%


  Images
Talar GOV Water Supply Scheme
Date: 02-08-2022

Talar GOV Water Supply Scheme
Date: 01-08-2022

Talar GOV Water Supply Scheme
Date: 07-06-2022

Talar GOV Water Supply Scheme
Date: 09-05-2022

Package Wise Report for Megha

# District Name Package Name Physical Progress Scheme Name Physical Progress Revised DPR Status Intake NOC Status Pert Chart Status Vetting Status Distribution System (KM) Overhead Tank CWR Intake Well Treatment Plant Raw Water Pumping Plant Clear Water Pumping Plant Staff Quarter
R S R S R S R S R S R S R S R S
1 Mirzapur Talar 74.77% Talar GOV Water Supply Scheme 74.77% Approved NOC Recieved View File Vetted by IIT | View File 827.2 509.37 15 15 6 6 1 1 1 1 1 1 6 6 8 4
2 Mirzapur Gothaura & Dhaua 73.26%
Gothaura GOV Water Supply Scheme 80.12% Approved NOC Recieved View File Not Uploaded 653.5 396 12 12 7 7 1 0 1 1 1 0 7 7 9 0
Dhauha GOV Water Supply Scheme 66.4% Approved NOC Recieved View File Not Uploaded 1067.04 461 25 24 11 11 1 1 1 1 1 1 11 11 13 2
Mirzapur Total 73.76% 73.76% 2547.74 1366.37 52 51 24 24 3 2 3 3 3 2 24 24 30 6
Grand Total 2547.74 1366.37 52 51 24 24 3 2 3 3 3 2 24 24 30 6
Note: Package Average is based on Schemes.