Jalaun
District Progress
  District:   

Jalaun


  No. of Packages:   


  No. of Schemes:   


  PMC:   


  Physical Achievement:   

61.35%


  Increment in Phy. Ach. (since 24th March):   

  Contractors
Name of Contractor No. of Packages No. of Schemes
Brij-Gopal 1 4
GVPR 1 1
Grand Total 2 5

  Components Progress    
Click on values of each component to view details
  Land WTP :


  Land Other :


  Intake Well :


  Treatment Plant :


  Clear Water Rising Main :


  CWR :


  Overhead Tank :


  Distribution System :


  Boundary Wall :


  Raw Water Pumping Plant :


  Clear Water Pumping Plant :


  Staff Quarter :


  Other NOCs :

2 / 23


  Pipeline (KM) :


Package Wise Report for Jalaun

# District Name Package Name Contractor Name Work Timings No. of Pending Bills Financial Progress Increment in Financial Achievement (since 24th March) Physical Progress Increment in Physical Achievement (since 24th March) Scheme Name Physical Progress Revised DPR Status Intake NOC Status Pert Chart Status Vetting Status Pipeline Components
Total Pipeline (KM) (DS+CWRM+RWRM) Distribution System (KM) Clear Water Rising Main (KM) Raw Water Rising Main (KM) Overhead Tank CWR Intake Well Treatment Plant Raw Water Pumping Plant Clear Water Pumping Plant Staff Quarter
R S R S R S R S R S R S R S R S R S R S R S
1 Jalaun Sala GVPR   Day
0 40.93% 24.89% 61.86% 0% Sala GOV Water Supply Scheme 61.86% Approved NOC Recieved View File Vetted by IIT | View File 1304.351 370.64
71.38 KM
912.13 174.57
20.23 KM
372.57 190.52
45.6 KM
19.651 5.55
5.55 KM
51 38 (40%)
11%
12 10 (37%)
12%
1 1 (13%)
13%
1 1 (60%)
13%
3 0 (0%)
0%
52 0 (0%)
0%
20 6 (1%)
1%
2 Jalaun Kota Mustkil, Madhepur Raipur & 270 Tubewell Brij-Gopal   Day
0 21.91% 18.97% 61.09% 0%
Kota-Mustakil GOV Water Supply Scheme 70.72% Approved NOC Recieved View File Not Uploaded 295.99 45.7
33.97 KM
214.14 23.6
20.06 KM
79.7 20.1
12.76 KM
2.15 2
1.15 KM
16 1 (11%)
8%
5 2 (16%)
13%
1 1 (20%)
20%
1 1 (13%)
10%
4 0 (0%)
0%
34 0 (0%)
0%
8 1 (10%)
9%
Madhepura GOV Water Supply Scheme 50.93% Approved NOC Recieved View File Not Uploaded 274.43 32.1
20.79 KM
202.38 9.8
9.2 KM
70.2 20.8
10.91 KM
1.85 1.5
0.68 KM
11 1 (16%)
15%
6 4 (20%)
16%
1 1 (25%)
24%
1 1 (30%)
26%
4 0 (0%)
0%
30 1 (0%)
0%
9 2 (12%)
10%
Tube well scheme(270 Nos) 31.2%
71 Boring Completed
0 ESR / OHT Work Completed
13 Boundary Wall Completed
Approved Not R View File Not Uploaded 1446.581 562
42.7 KM
1431.675 560.8
42.7 KM
0 0
0
14.906 1.2
0
270 20 (21%)
18%
0 0 (0%)
0%
0 0 (0%)
0%
0 0 (30%)
30%
274 165 (65%)
4%
0 0 (0%)
0%
262 59 (24%)
12%
Raippur GOV Water Supply Scheme 52.17% Approved NOC Recieved View File Not Uploaded 350.969 89.31
37.79 KM
264.315 37.6
21.4 KM
85.654 51.1
16.38 KM
1 0.61
0.01 KM
17 3 (20%)
16%
13 6 (25%)
20%
1 1 (28%)
26%
1 1 (35%)
24%
4 0 (0%)
0%
58 1 (0%)
0%
16 2 (25%)
11%
Jalaun Total 29.54% 21.93% 61.35% 0% 61.35% 3672.321 1099.75 3024.64 806.37 608.124 282.52 39.557 10.86 365 63 36 22 4 4 4 4 289 165 174 2 315 70
Grand Total 3672.321 1099.75 3024.64 806.37 608.124 282.52 39.557 10.86 365 63 36 22 4 4 4 4 289 165 174 2 315 70
*The district Physical Progress Average does not include the schemes started within last 6 months.