District: Banda
|
1 |
Amli kaur G.O.V. W/S Scheme & Tube well scheme(28 Nos) |
N.C.C |
04-04-2022 |
Nari-ESR |
View File |
04-04-2022 |
Amlikaur CWR-9 (3100 KL) Excavation Work under progress
|
View File |
15-02-2022 |
ESR Work is in Progress |
View File |
25-01-2022 |
Plate compactor at Kaji Tola (Baberu Block) for 900mm & 450mm DI K9-(J5 to J27) |
View File |
13-01-2022 |
|
View File |
12-01-2022 |
Dewatering work is in Progress |
View File |
20-12-2021 |
Excavation started for 225 KL OHT Santar - Baberu Block. |
View File |
16-12-2021 |
HSC Connection in Progress |
View File |
11-12-2021 |
Safety Training to the Labours of WTP. |
No file Uploaded |
11-12-2021 |
PCC of Mata OHT-500KL Completed. |
View File |
09-12-2021 |
Koraree ESR Work is in Progress |
View File |
29-11-2021 |
Patnapurwa-ESR Work is in Progress |
View File |
19-11-2021 |
Hydro testing Benda Village Tinwbari Block. |
View File |
17-11-2021 |
Compressor cleaning of Bore well at Kuchoulee village Kamasin block.
|
View File |
25-10-2021 |
Koraree Oht column steel work in progress for staging final column lift. |
View File |
25-10-2021 |
Raft steel binding in progress at badaoulee OHT 250 KL, 18 mtr Stagging Baberu Block. |
View File |
19-10-2021 |
CLF 1 Main wall Raft steel in progress |
View File |
19-10-2021 |
Flash Mixer 2, 1st lift shuttering Completed |
No file Uploaded |
18-10-2021 |
Raft steel binding inprogress at Kuchauli-Kamasin Block |
View File |
18-10-2021 |
CLF 1 Main wall PCC Completed at WTP |
View File |
12-10-2021 |
Mahokhar OHT, Barokhar Khurd Block |
View File |
12-10-2021 |
Intake 3rd lift cast Work in progress, Amlikaur WSS Banda |
View File |
11-10-2021 |
Intake WELL 3RD LIFT SHUTRING COMPLETED |
View File |
11-10-2021 |
Chaukipurwa (DANDAMAU- Jaspura ) OHT RAFT REINFORCEMENT work wip |
View File |
06-10-2021 |
Barokhar Khurd OHT column concrete above 3rd brace 2nd lift |
View File |
06-10-2021 |
Trunch For HDPE Pipe Laying Byonja-Tindwari Block |
View File |
05-10-2021 |
Checked discharge of tube well pump at Baragaon and found ok |
View File |
01-10-2021 |
Flash mixer 2 Raft reinforcement work is in progress |
View File |
01-10-2021 |
Shuttering work Completed of column below GL at Rehutan ESR-250KL |
View File |
29-09-2021 |
Kapritha khurd (Jaspura) HDPE pipe jointing work in Progress |
View File |
27-09-2021 |
Raft reinforcement work in progress at padohara ESR |
View File |
22-09-2021 |
Binding of Reinforcement work in progress at Patvan Baberu Block. |
View File |
21-09-2021 |
Excavation work completed at Kuchoulee village kamasin block |
View File |
17-09-2021 |
Arsaunda Village Excavation work is in progress for HDPE Distribution line (140mm) from J-128 to J-18 |
View File |
16-09-2021 |
intake well is in Progress |
View File |
14-09-2021 |
WTP CLF Column Footing Steel Binding in progress |
View File |
09-09-2021 |
Dohatara OHT-400KL. |
View File |
08-09-2021 |
Feeding ramp work in progress. |
View File |
07-09-2021 |
Steel binding work in progress at Bhadvari ESR Baberu Block. |
View File |
04-09-2021 |
Soil cutting and shifting work under progress from clear water sump area at WTP jalalpur |
View File |
02-09-2021 |
600 mm dia DI pipe laying work in progress |
View File |
01-09-2021 |
2nd lift Kerb Concrete started at Intake well |
View File |
31-08-2021 |
Excavation work in progress for 75 kl ESR at Aadri village |
View File |
30-08-2021 |
Bhumi Poojan for Tubewell bore at Narayan village under Jaspura block in presence of SHO Jaspura Block and Village Pradhan, PMC & NCC Staff |
View File |
27-08-2021 |
Raw materials sampling done at Godhani OHT Tindwari block for testing purpose. |
View File |
26-08-2021 |
|
View File |
25-08-2021 |
DI 350mm K-9 pipe laying & jointing work is in under progress at Bishandi khurd village {Barokhar khurd Block} |
View File |
19-08-2021 |
Clariflocculator central shaft excavation work in progress at WTP |
View File |
18-08-2021 |
Clariffloculator central shaft excavation work in progress at WTP |
View File |
14-08-2021 |
DI pipe 600mm unloading at marka road. |
View File |
12-08-2021 |
Pachulla 100KL ESR 3rd Bracing shuttring work is in progress. |
View File |
11-08-2021 |
Mahokhar OHT reached till GL |
View File |
07-08-2021 |
Hateti purwa OHT Excavation work in progress in Barokhar khurd block
|
View File |
06-08-2021 |
Steel binding work of raft Beam in progress Arsonda |
View File |
03-08-2021 |
Intake Well 2nd lift in Progress |
View File |
30-07-2021 |
Heavy Rain Creating Huge Interruptions |
View File |
27-07-2021 |
Kerb 1st lift deshuttering work & 2 nd lift Shuttering Work is in progress at Intake well . |
View File |
24-07-2021 |
900mm Dia DI pipe laying work is in progress near Miya Baraulee Baberu Block |
View File |
23-07-2021 |
Intake Well Kerb Concreting is in Progress |
View File |
22-07-2021 |
Filter house land cutting work under progress at WTP Jalalpur |
View File |
21-07-2021 |
Admin building footing shuttering work in progress at WTP Jalalpur |
View File |
20-07-2021 |
OHT 150KL steel binding work in progress at wtp jalalpur |
View File |
19-07-2021 |
Concrete Kerb Work is in Progress |
View File |
17-07-2021 |
Admin building footing steel binding work in progress at WTP. |
View File |
15-07-2021 |
Steel Binding is in progress at intake well |
View File |
13-07-2021 |
Steel Binding work is in progress at Intake well. |
View File |
12-07-2021 |
Jalalpur OHT Raft Steel Binding in progress at WTP |
View File |
10-07-2021 |
Casting work is under progress of Raft foundation at Sahoorpur (OHT-350KL)-Tindwari Block |
View File |
08-07-2021 |
Jalalpur OHT 150KL PCC completed at WTP |
View File |
07-07-2021 |
Inner shuttering for kerb of intake well is in progress..
|
View File |
06-07-2021 |
Welding work of cutting edge is in progress for kerb at intake well |
View File |
05-07-2021 |
Welding of Cutting edge at intake well is in progress. |
View File |
03-07-2021 |
TMT steel 16 mm & 20 mm unloading work in progress at WTP Jalalpur |
View File |
02-07-2021 |
Admin building footing dressing work in progress at wtp |
View File |
01-07-2021 |
Admin building footing excavation work completed |
View File |
30-06-2021 |
PCC for_OHT Foundation work in progress at SAHOORPUR_ Palhara |
View File |
29-06-2021 |
PCC work in progress at Khari village |
View File |
26-06-2021 |
Levelling and extra soil cutting work completed at Amlikaur location. |
View File |
25-06-2021 |
Weather Condition in Baberu Block on 25-06-2021 |
View File |
25-06-2021 |
Rain in Amlikaur, Tindwari Block |
View File |
24-06-2021 |
DI fittings stacking work in progress at WTP Jalalpur |
View File |
23-06-2021 |
Shuttering Material unloading work in progress at WTP Jalalpur |
View File |
22-06-2021 |
Soil shifting from staff quarter area at WTP JALALPUR |
View File |
22-06-2021 |
Soil shifting from staff quarter area at WTP JALALPUR |
View File |
21-06-2021 |
Cutting & Levelling work under progress for Staff Quarters at WTP Jalalpur |
View File |
18-06-2021 |
Brickwork started at Tharthuwa village (Baberu Block) . |
View File |
17-06-2021 |
Brick masonry work in progress at Mahui vallage-Tindwari block |
View File |
16-06-2021 |
MCWR area cutting work in progress at WTP-Jalalpur |
View File |
14-06-2021 |
Brick masonry work in progress at Mahui village |
View File |
11-06-2021 |
Intake Well approach road work is in progress... |
View File |
10-06-2021 |
Inspection by SDM sir at Mahokhar Site OHT. |
View File |
09-06-2021 |
Aggregate reached at lasada village for boundary wall. Jaspura block |
View File |
08-06-2021 |
Jaspura block lasada village boundary wall excavation work. |
View File |
08-06-2021 |
At Baragaon village, lasada village, madauli khurd village, narayan village Work was halted for 07-06-2021 due to rain |
View File |
07-06-2021 |
Village Badoulee, Boundary Wall Brickwork is in progress |
View File |
05-06-2021 |
CLF3 and CLF4 cutting work is in progress at WTP |
View File |
02-06-2021 |
Pipeline work is under progress at Lama(DI K-9 400mm) |
View File |
01-06-2021 |
CLF3 and CLF4 Cutting work in progress at WTP |
View File |
31-05-2021 |
CLF3 & CLF4 Cutting work in progress at WTP (Jalalpur Village, Baberu Block) |
View File |
29-05-2021 |
Excavation at CLF3 & CLF4 in Jalalpur Village at WTP in Progress |
View File |
28-05-2021 |
Clearing and Excavation for Boundary Wall Started |
View File |
28-05-2021 |
PCC Work Complete at Mawai Buzurg |
View File |
27-05-2021 |
400 mm dia DI pipeline laying J-152 to J-27 , Near Shapur village |
No file Uploaded |
26-05-2021 |
"Jal Nigam-JE sir" visited to Achhah site Boundary wall. |
View File |
25-05-2021 |
Excavation Work is in Progress for DI-Pipe Laying |
View File |
24-05-2021 |
1.Pipe laying excavation work is in progress at J-152 to J-27 |
View File |
24-05-2021 |
2.Layout work for Boundry Wall Mahui village (TINDWARI-BLOCK) |
View File |
22-05-2021 |
Brickwork for Boundary wall is in progress at Achhah village. Baberu Block. |
View File |
22-05-2021 |
Brickwork for Boundary Wall is in progress at Achhah village, Baberu Block. |
View File |
22-05-2021 |
400 mm Dia DI-K9 Pipe laying work is in progress |
View File |
21-05-2021 |
Ramp formation at Intake Well |
View File |
20-05-2021 |
Work Progress was Halted for a Day due to Heavy Rain in Banda |
View File |
19-05-2021 |
Boundary Wall Construction Completed
|
View File |
18-05-2021 |
400 mm Dia-K9 Pipe laying work progress at J-152 to J-27 Baberu Block |
View File |
17-05-2021 |
Ramp and platform is ready and Left side ramp is backfilling by soil. |
View File |
17-05-2021 |
400 mm Dia-K9 Pipe laying work progress at J-152 to J-27 Baberu Block |
View File |
15-05-2021 |
Construction of Boundary Wall at Achhah Village |
View File |
13-05-2021 |
1.Brick masonry work progress at koraree village |
No file Uploaded |
12-05-2021 |
Jaspura block boundary wall excavation work. Location- Baragaon village |
No file Uploaded |
12-05-2021 |
Jaspura block boundary wall excavation work. Location- Baragaon village |
No file Uploaded |
11-05-2021 |
Excavation for Pipeline work in progress |
No file Uploaded |
10-05-2021 |
PCC work progress at Achhah village |
No file Uploaded |
10-05-2021 |
Boundary Wall Construction at Mata Village |
No file Uploaded |
08-05-2021 |
Koraree Boundary wall work is in progress |
No file Uploaded |
07-05-2021 |
Pipe Laying work is in progress at Tindwari block |
No file Uploaded |
07-05-2021 |
Pipe Laying work is in progress at Tindwari block |
No file Uploaded |
06-05-2021 |
Achhah Village Boundary wall dressing work in progress |
No file Uploaded |
04-05-2021 |
Pipe laying at Gogauli Village |
No file Uploaded |
03-05-2021 |
Baberu Block
Village-Koraree
Boundary wall brick masonry work is in progress |
No file Uploaded |
01-05-2021 |
Luktara Barokhar khurd block Boundary wall Layout work under progress |
No file Uploaded |
01-05-2021 |
Luktara Barokhar khurd block Boundary wall Layout work under progress |
No file Uploaded |
01-05-2021 |
Luktara Barokhar khurd block Boundary wall Layout work under progress |
No file Uploaded |
01-05-2021 |
Luktara Barokhar khurd block Boundary wall Layout work under progress |
No file Uploaded |
30-04-2021 |
Excavation complete for boundary wall at Achhah village - Baberu block |
No file Uploaded |
29-04-2021 |
Excavation work is in Progress.
(Our Team is mourning the sudden demise of our hard-working employee Mr. Devender, we request you to co-operate any kind of delays in sending the required data or replying to your Emails.) |
No file Uploaded |
28-04-2021 |
Both JCB are working for Ramp and platform at Intake Well |
No file Uploaded |
27-04-2021 |
JCB are working for Ramp and Platform construction.. |
No file Uploaded |
26-04-2021 |
Arsaunda village (Compound Wall) Construction under Progress |
No file Uploaded |
24-04-2021 |
600mm Dia pipe laying at Goguli Village |
No file Uploaded |
23-04-2021 |
Recently after conducting Covid test on our staff members, we were enlightened that few of our staff members are COVID+ve, due to this unfavourable situation we forced to quarantine our staff, even after being sick our team is trying their best to meet the daily deadlines of the work.
So it is our humble request to please co-operate any kind of delay in responding to your Emails or in providing the required data.
We are trying our best to avoid and sort of delay.
|
No file Uploaded |
22-04-2021 |
1.Boundary Wall im progress at different locations.
2.Pipe Laying Work in progress
3.Covid patients are found in our office due to work is hampering |
No file Uploaded |
21-04-2021 |
Boundary Wall Demarcation for Madauli Khurd |
No file Uploaded |
20-04-2021 |
Construction of Ramp and Platform is in progress at Intake well.. |
No file Uploaded |
17-04-2021 |
Excavation work under Progress at CLF |
No file Uploaded |
17-04-2021 |
JCB are working at Intake well for Platform and Ramp.. |
No file Uploaded |
16-04-2021 |
Construction of Ramp and Platform is in progress for Intake well. |
No file Uploaded |
16-04-2021 |
Soil Levelling and Dressing work by JCB at WTP |
No file Uploaded |
16-04-2021 |
600 mm Dia K9 Pipe laying work in progress at Gugoli village. |
No file Uploaded |
15-04-2021 |
600 mm Dia K9 PiPe laying work in progress at Gugoli village. |
No file Uploaded |
14-04-2021 |
Brick Masonry work of Compound wall at Arsounda Village |
No file Uploaded |
14-04-2021 |
Excavation work is in progress at WTP, CLF1 & CLF2 |
No file Uploaded |
14-04-2021 |
Pipe laying work is in progress at Gugoli village. |
No file Uploaded |
13-04-2021 |
Excavation work is in progress up at WTP, CLF1 & CLF2 , 80% excavation completed. |
No file Uploaded |
13-04-2021 |
Excavation work progress at koraree village for Boundary Block |
No file Uploaded |
12-04-2021 |
Excavation of extra soil at WTP, CLF area |
No file Uploaded |
12-04-2021 |
JCB working for platform at Intake well. |
No file Uploaded |
10-04-2021 |
Jalalpur Village, Baberu Block. CLF AREA EXCAVATION WORK IS IN PROGRESS |
No file Uploaded |
09-04-2021 |
Platform for Intake well is in progress... |
No file Uploaded |
08-04-2021 |
CLF area excavation work is in progress WTP, Jalalpur Village, Baberu Block |
No file Uploaded |
07-04-2021 |
Pipe laying started in Gugouli Village |
No file Uploaded |
06-04-2021 |
Excavation work completed of Boundary wall at Bhindaura village(OHT), Tindwari Block |
No file Uploaded |
06-04-2021 |
Safety Measures Ensured to Prevent Public Casualties |
No file Uploaded |
05-04-2021 |
Today Excavation work completed of Compound wall at Bhindaura village (OHT) |
No file Uploaded |
03-04-2021 |
Construction of Cofferdam or Platform for Intake well is in progress.. |
No file Uploaded |
02-04-2021 |
Bypass Road from WTP to intake well is in progress.. |
No file Uploaded |
01-04-2021 |
DI Pipe 500 mm K9 unloading work start at Aliya village main road of Banda |
No file Uploaded |
31-03-2021 |
Site office and Lab Work in Progress |
No file Uploaded |
30-03-2021 |
Soil cutting work in progress at WTP, CLF area |
No file Uploaded |
30-03-2021 |
Road rectification work in progress near amlikaur pond |
No file Uploaded |
30-03-2021 |
Road rectification work in progress near amlikaur pond |
No file Uploaded |
27-03-2021 |
Extra soil cutting work in progress at WTP, CLF area by Poclain |
No file Uploaded |
27-03-2021 |
Extra soil cutting work in progress at WTP, CLF area by Poclain |
No file Uploaded |
26-03-2021 |
Bushes, Bamboo tree cutting work under progress at OHT/CWR (Amlikaur) Location, Tindwari Block |
No file Uploaded |
25-03-2021 |
Ground Clearing and Levelling at WTP Jalalpur Village |
No file Uploaded |
24-03-2021 |
1.Out of 87Now 86 received.
2.Applied for Intake well in CWC office Banda .
3. 800dia K-9 Pipes unloading.
4. 700dia Pipes K-9 unloading.
5. 900dia k-9 pipes unloading. |
No file Uploaded |
23-03-2021 |
1.700mm Dia Pipes K9 Unloading
2.800mm Dia Pipes K9 Unloading
3.900mm Dia Pipes K9 Unloading
Resistivity Survey, SPT Survey Completed |
No file Uploaded |
22-03-2021 |
1.Out of 87Now 86 received.
2.Applied for Intake well in CWC office Banda .
3. 800dia K-9 Pipes unloading.
4. 700dia Pipes K-9 unloading.
5. 900dia k-9 pipes unloading. |
No file Uploaded |
20-03-2021 |
1.Out of 87Now 86 received.
2.Applied for Intake well in CWC office Banda .
3. 800dia K-9 Pipes unloading.
4. 700dia Pipes K-9 unloading.
5. 900dia k-9 pipes unloading. |
No file Uploaded |
19-03-2021 |
1.Out of 87Now 86 received.
2.Applied for Intake well in CWC office Banda .
3. 800dia K-9 Pipes unloading.
4. 700dia Pipes K-9 unloading.
5. 600dia k-9 pipes unloading. |
No file Uploaded |
18-03-2021 |
1.Out of 87Now 86 received
2.Applied for Intake well in CWC office Banda
3. 800dia K-9 Pipes unloading
4. 700dia Pipes K-9 unloading
5. 600dia k-9 pipes unloading |
No file Uploaded |
17-03-2021 |
1.Out of 87Now 86 received
2.Applied for Intake well in CWC office Banda
3. 800dia K-9 Pipes unloading
4. 700dia Pipes K-9 unloading
5. 600dia k-9 pipes unloading |
No file Uploaded |
16-03-2021 |
1.Out of 87Now 86 received
2.Applied for Intake well in CWC office Banda
3. 800dia K-9 Pipes unloading
4. 700dia Pipes K-9 unloading
5. 600dia k-9 pipes unloading |
No file Uploaded |
15-03-2021 |
1.Out of 87Now 86 received
2.Applied for Intake well in CWC office Banda
3. 800dia K-9 Pipes unloading
4. 700dia Pipes K-9 unloading
5. 600dia k-9 pipes unloading
|
No file Uploaded |
14-03-2021 |
1.Out of 87Now 86 received
2.Applied for Intake well in CWC office Banda
3. 800dia K-9 Pipes unloading
4. 700dia Pipes K-9 unloading
5. 600dia k-9 pipes unloading |
No file Uploaded |
13-03-2021 |
1.Out of 87Now 86 received
2.Applied for Intake well in CWC office Banda
3. Survey Work & soil testing is completed
4. 800dia K-9 Pipes unloading
5. 700dia Pipes K-9 unloading
6. 600dia k-9 pipes unloading |
No file Uploaded |
12-03-2021 |
1.Out of 87Now 86 received
2.Applied for Intake well in CWC office Banda
3. Survey Work & soil testing is completed
4. 800 Dia K-9 Pipes unloading
5. 700 dia Pipes K-9 unloading
6. 600 dia pipes unloading |
No file Uploaded |
2 |
khatan G.O.V. W/S Scheme |
L&T |
|
|
|
District: Chitrakoot
|
3 |
Raipura G.O.V. W/S Scheme |
GVPR |
|
|
|
4 |
Silauta mustkil G.O.V. W/S Scheme |
L&T |
12-03-2021 |
NOC required: Pipe water supply scheme for Silauta Mustakil & Chandi Bangar. |
No file Uploaded |
12-03-2021 |
Permission required for Railway Crossings |
No file Uploaded |
12-03-2021 |
NOC of Chandi Bangar WTP required |
No file Uploaded |
12-03-2021 |
Permission required for Pipe Laying /Crossing |
No file Uploaded |
12-03-2021 |
List of Support Required from your end pertaining to Silauta Mustakil & Chandi Bangar WSS. |
No file Uploaded |
12-03-2021 |
Regarding permission of NOC for mining Materials |
No file Uploaded |
12-03-2021 |
Confirmation on Size Selection of Air Valve & Scour Valve for installation in Pipeline |
No file Uploaded |
12-03-2021 |
No Proper approach available for newly identified Chandi Bangar WTP location |
No file Uploaded |
12-03-2021 |
Reg. Silauta Mustakil alternate proposed location |
No file Uploaded |
12-03-2021 |
Reg. Forest Land clearance for pipe laying activities |
No file Uploaded |
12-03-2021 |
Ongoing Hindrances at Silauta Mustakil WTP |
No file Uploaded |
12-03-2021 |
Silauta Mustakil alternate proposed Intake Location |
No file Uploaded |
12-03-2021 |
Submission of Mix Design of Concrete |
No file Uploaded |
12-03-2021 |
Forest Land clearance for making approach towards SM WTP |
No file Uploaded |
12-03-2021 |
Administration clearance for making permanent approach towards SM WTP |
No file Uploaded |
12-03-2021 |
Regarding Electrical pole shifting |
No file Uploaded |
12-03-2021 |
Regarding ROW Clearance |
No file Uploaded |
12-03-2021 |
Regarding Hindrances in land finalization |
No file Uploaded |
12-03-2021 |
Reg. Road Cutting Permission |
No file Uploaded |
12-03-2021 |
Reg. Permission required from various departments |
No file Uploaded |
12-03-2021 |
Reg. Approval of Mix Design of Concrete |
No file Uploaded |
12-03-2021 |
Hindrances pertaining to Silauta Mustakil Intake Well |
No file Uploaded |
12-03-2021 |
Confirmation on Size Selection of Air Valve & Scour Valve for installation in Pipeline |
No file Uploaded |
12-03-2021 |
Reg. Approval of Mix Design of Concrete |
No file Uploaded |
12-03-2021 |
Reg. updated NOC required |
No file Uploaded |
12-03-2021 |
Reg. Permission required for Railway Crossings |
No file Uploaded |
12-03-2021 |
Reminder Reg. Hindrances in Land Finalization, handing over & NOC of the lands. |
No file Uploaded |
12-03-2021 |
Reg. Approval of Mix Design of Concrete |
No file Uploaded |
12-03-2021 |
Reg. updated NOC required |
No file Uploaded |
12-03-2021 |
Time Extension |
No file Uploaded |
5 |
Chandi Bangar G.O.V. W/S Scheme |
L&T |
16-06-2021 |
SMCB Revised BOQ Approved including Bhartaul Scheme |
View File |
12-03-2021 |
Revised Layout plan of intake Wells. |
No file Uploaded |
12-03-2021 |
Hindrances for Chandi Bangar WTP location |
No file Uploaded |
District: Hamirpur
|
6 |
Haraulipur G.O.V. W/S Scheme |
M/s PNC Infra Tech & SPML (JV)
|
|
|
|
7 |
Patoradanda G.O.V. W/S Scheme |
M/s SPML-JWIL (JV) |
|
|
|
7 |
125 Tube well Schemes in Blocks (Gohand, Muskra, Sarila and Rath) |
M/s PNC Infra Tech & SPML (JV)
|
|
|
|
District: Jalaun
|
8 |
Madhepura GOV Water Supply Scheme |
Brij-Gopal & SPML (JV)
|
|
|
|
9 |
Raippur GOV Water Supply Scheme |
Brij-Gopal & SPML (JV)
|
|
|
|
10 |
Kota-Mustakil GOV Water Supply Scheme |
Brij-Gopal & SPML (JV)
|
|
|
|
11 |
Tube well scheme(270 Nos) |
Brij-Gopal & SPML (JV)
|
|
|
|
12 |
Sala GOV Water Supply Scheme |
GVPR Infra Ltd. |
02-04-2021 |
NOC & APPROACH TO INTAKE WELL LAND REQUIRE. ALSO LAND NEED FOR RAW WATER PUMPING MAIN. |
No file Uploaded |
02-04-2021 |
QAP OF FITTINGS SUBMITTED TO EE UPJN FOR APPROVAL PROCESS. |
No file Uploaded |
02-04-2021 |
As per Revised Approved DPR. 13-14 NO.S of New Land require for OHTs. Details submitted to PMC. TILL NOT RECEIVED. |
No file Uploaded |
02-04-2021 |
AS PER MANUFACTURE OF DI PIPES(TATA). Soon after all process of inspection. PIPE SUPPLY TARGETED UPTO 10/04/2021. |
No file Uploaded |
02-04-2021 |
QAP OF HDPE PIPES SUBMITTED TO SE SWSM BY 25/03/2021 FOR APPROVAL.
QAP OF HDPE FITTINGS SUBMITTED TO EE UPJN BY 01/04/21 FOR APPROVAL PROCESS. |
No file Uploaded |
02-04-2021 |
Boundary wall works will start in next week. Formal approval need from SWSM on Drawing of boundary wall. Technical SACTION has approved.pl suggest. |
No file Uploaded |
01-04-2021 |
NOC OF INTAKE WELL NEED ON PRIORITY |
No file Uploaded |
25-03-2021 |
QAP of HDPE pipes submitted to EE MPJN,ORAI & PMC JALAUN for further process & approval. |
No file Uploaded |
24-03-2021 |
Boundary wall drawing approval require from SWSM. |
No file Uploaded |
24-03-2021 |
As per approved DPR. New Location require for some OHTs. List of villages given to PMC( JALAUN) |
No file Uploaded |
24-03-2021 |
New. Land require. |
No file Uploaded |
24-03-2021 |
NOC INTAKE NOT RECEIVED TILL. |
No file Uploaded |
19-03-2021 |
Please kindly arrange NOC of Intake well. |
No file Uploaded |
19-03-2021 |
Please kindly arrange the assess route through govt. Land upto intake well Location. For movement of machineries , staff vehicals, stack of construction materials. |
No file Uploaded |
18-03-2021 |
NOC for Intake well from irrigation not received till date. |
No file Uploaded |
15-03-2021 |
Boundary wall drawing pending at Technical SACTION.SWSM. |
No file Uploaded |
District: Jhansi
|
13 |
Gulara GOV Water Supply Scheme |
N.C.C |
|
|
|
14 |
Bacholi Buzurg GOV Water Supply Scheme |
N.C.C |
|
|
|
15 |
Tilaetha GOV Water Supply Scheme |
N.C.C |
|
|
|
16 |
Burhpura GOV Water Supply Scheme |
N.C.C |
|
|
|
17 |
Kuraicha GOV Water Supply Scheme |
I.H.P |
30-04-2021 |
Design and Drawing pending for Approval. |
No file Uploaded |
18 |
Imlota GOV Water Supply Scheme |
Brij-Gopal & Bhuratnam |
|
|
|
19 |
Purwa GOV Water Supply Scheme |
Dara Engineering & Infrastructure Ltd. |
19-05-2021 |
D&D of various components as mentioned in the attached letter for Puruwa GoV has been submitted in soft copy and mailed for verification. Due to Pandemic it is found difficult to submit the Hard Copies. |
View File |
19-05-2021 |
Proposal for acquisition of private land to reach Intake site for the construction at Puruwa GoV. |
View File |
19-05-2021 |
SUbmission of D&D for OHT in soft copies for Puruwa GoV |
View File |
19-05-2021 |
Attached submission details and their status as on today. |
View File |
20 |
Barwar GOV Water Supply Scheme |
Unipro Techno Infrastructure |
03-07-2021 |
Dhurwai ESR-07 EXCAVATION WORK STARTED |
View File |
17-04-2021 |
QAP of DI Pipe has been first submitted
0n 28-12-20,
2nd submission is also done 17-03-21
still not approved.Waiting |
No file Uploaded |
21 |
Barthari GOV Water Supply Scheme |
Brij-Gopal & Bhuratnam (JV)
|
|
|
|
22 |
Teaharka GOV Water Supply Scheme |
Brij-Gopal & Bhuratnam (JV)
|
|
|
|
District: Lalitpur
|
23 |
Tori GOV Water Supply Scheme |
Banco Const & Ganga Infra |
|
|
|
24 |
Chandawali GOV Water Supply Scheme |
Bri Eng & Banco Const
|
|
|
|
25 |
Badanpur GOV Water Supply Scheme |
Dara Engineering & Infrastructure Ltd. |
19-05-2021 |
D&D of various components as mentioned in the attached letter for Badanpur GoV has been submitted in soft copy and mailed for verification. Due to Pandemic it is found difficult to submit the Hard Copies. |
View File |
26 |
Dhorra Balabehat GOV Water Supply Scheme |
Gayatri & Ramky (JV)
|
|
|
|
27 |
Jaklaun Birdha GOV Water Supply Scheme |
Gayatri & Ramky (JV)
|
|
|
|
28 |
Kadesara Kalan GOV Water Supply Scheme |
Gayatri & Ramky (JV)
|
|
|
|
29 |
Sojana Gurhga GOV Water Supply Scheme |
Dara Engineering & Infrastructure Ltd. |
19-05-2021 |
D&D of various components for Sojna Gurha GoV submitted in soft copy and has been mailed as mentioned in the attached letter. Due to Pandemic it has been found difficult to submit the Hard Copies. |
View File |
30 |
Saidpur Kumheri GOV Water Supply Scheme |
J.M.C & J.W.I.L |
|
|
|
31 |
Gona Narhat GOV Water Supply Scheme |
J.M.C & J.W.I.L |
22-08-2021 |
Madanpur OHT PCC was done on 31.005.2021. Due to Archeology land issue work stopped till 01.06.2021. |
View File |
22-08-2021 |
Madanpur OHT PCC was done on 31.005.2021. Due to Archeology land issue work stopped till 01.06.2021. |
View File |
22-08-2021 |
Madanpur OHT PCC was done on 31.005.2021. Due to Archeology land issue work stopped till 01.06.2021. |
View File |
32 |
Kachnoda Kalan GOV Water Supply Scheme |
Gayatri & Ramky (JV) |
|
|
|
33 |
Sukul Guwan GOV Water Supply Scheme |
Dara Engineering & Infrastructure Ltd. |
19-05-2021 |
D&D of various components as mentioned in the attached letter for Sukul Guwan GoV has been submitted in soft copy and mailed for verification. Due to Pandemic it is found difficult to submit the Hard Copies. |
View File |
34 |
Lagaon GOV Water Supply Scheme |
Gayatri & S.P.M.L |
|
|
|
35 |
Mandawara GOV Water Supply Scheme |
Dara Engineering & Infrastructure Ltd. |
19-05-2021 |
D&D of various components as mentioned in the attached letter for Mandawara GoV has been submitted in soft copy and mailed for verification. Due to Pandemic it is found difficult to submit the Hard Copies. |
View File |
13-05-2021 |
DPR has been submitted in soft copy via mail. It has been found difficult to submit hard copies in this Pandemic. |
No file Uploaded |
36 |
Masora Sindwaha GOV Water Supply Scheme |
J.M.C & J.W.I.L |
|
|
|
37 |
Billa Mogan GOV Water Supply Scheme |
Dara Engineering & Infrastructure Ltd. |
|
|
|
District: Mahoba
|
38 |
kabrai G.O.V. W/S Scheme |
N. K. Gupta Contractor & K.B. Gupta Contractor (JV) |
|
|
|
39 |
Salaiya Nathupura G.O.V. W/S Scheme |
J.M.C & J.W.I.L |
|
|
|
40 |
Lahchura kashipura G.O.V. W/S Scheme |
J.M.C & J.W.I.L |
|
|
|
41 |
Shivhar G.O.V. W/S Scheme |
L&T |
20-03-2021 |
Our Letter No. LTCD/SRWSS/2020-21/39 Dated 5th Oct 2020 (Regarding Construction of Intake well at Chandrawal Dam and Laying of Pipeline along the Irrigation boundary and canal crossing at various villages) |
No file Uploaded |
20-03-2021 |
Our Letter No. LTCD/SRWSS/2020-21/39 Dated 5th Oct 2020 (Regarding Construction of Intake well at Chandrawal Dam and Laying of Pipeline along the Irrigation boundary and canal crossing at various villages) |
No file Uploaded |
20-03-2021 |
Our Letter No. LTCD/SRWSS/2020-21/49 Dated 16th Oct 2020(Regarding Ongoing Hindrances in Project activities) |
No file Uploaded |
20-03-2021 |
Our Letter No. LTCD/SRWSS/2020-21/51 Dated 16th Oct 2020 (Regarding Railway crossing permission for laying of 200mm dia. DI distribution pipeline) |
No file Uploaded |
20-03-2021 |
Our Letter No. LTCD/SRWSS/2020-21/52 Dated 17th Oct 2020 (Reg. National Highway (NH-34) crossing permission for laying of 350mm dia. DI pipeline) |
No file Uploaded |
20-03-2021 |
Our Letter No. LTCD/SRWSS/2020-21/57 Dated 17th Oct 2020 (Reg. Permission of Intake Well at Chandrawal dam) |
No file Uploaded |
20-03-2021 |
Our Letter No. LTCD/SRWSS/2020-21/59 Dated 26th Oct 2020 (Reg. State Highway MDR 15 B crossing permission for laying of 100mm 200mm dia. DI pipeline) |
No file Uploaded |
20-03-2021 |
Our Letter No. LTCD/SRWSS/2020-21/79 Dated 24th Nov 2020 (Regarding Ongoing hindrances for DI pipe Laying process) |
No file Uploaded |
20-03-2021 |
Our Letter No. LTCD/SRWSS/2020-21/77 Dated 18th Nov 2020 (Regarding pending concerns/ Approvals) |
No file Uploaded |
19-03-2021 |
Our Letter No. LTCD/SRWSS/2020-21/35 Dated 1st Oct 2020 (Regarding Laying of Pipeline along with road boundary and road crossing permission) |
No file Uploaded |
17-03-2021 |
Our Letter No. LTCD/SRWSS/2020-21/32 Dated 28th Sept 2020 (Regarding NOC and land clearance status) |
No file Uploaded |
17-03-2021 |
Our Letter No. LTCD/SRWSS/2020-21/33 Dated 30th Sept 2020 (Regarding Clearance for laying of Pipeline through Forest) |
No file Uploaded |
17-03-2021 |
Our Letter No. LTCD/SRWSS/2020-21/34 Dated 1st Oct 2020 (Regarding NOC & Land clearance for pipe water supply scheme) |
No file Uploaded |
12-03-2021 |
Following Drawing approvals is pending with SWSM: -
1. Approach Bridge
2. Intake cum pump house.
3. WTP Structures (Cascade aerator, Inlet chamber, Inlet Channel, Flash mixer and drop chamber Clariflocculator, Filter House, Filter Annex Building, Chemical House, Chlorination room & Chlorine tonner room with Neutralization pit, Backwash Recirculation Sump, Sludge Sump and Admin building)
4. Clear water Reservoirs (CWR-1,2,4 & 5)
5. Clear Water Pump House (CWPH -2 & 5)
6. Overhead tanks (OHT-2,4,12 & 13)
7. Staff Quarters
|
No file Uploaded |
42 |
Dhawarra Sijwa G.O.V. W/S Scheme |
CLC-SMC JV |
|
|
|
District: Mirzapur
|
43 |
Ahugi Kala GOV Water Supply Scheme |
N.C.C |
25-03-2021 |
Total Pipe received at site 473/1157 (All length in Km).
1. DI K7-61.837/293
2. DI K9- 49/171
3. GI Medium- 362/692 |
No file Uploaded |
18-03-2021 |
Letter no-107 Dt: 17-03-2021.
Irrigation dept has asked to propose intake location 205m beyond dam as per attached letter. |
No file Uploaded |
17-03-2021 |
Intake - NOC for intake not yet received from Irrigation Dept.
Pipes received at site till date.
DI K7-61837 Rmt
DI K9-35672 Rmt
GI Medium - 362100 Rmt. |
No file Uploaded |
44 |
Gothaura GOV Water Supply Scheme |
Megha Engineering |
11-05-2022 |
1) All CWR Structures work in progress. |
No file Uploaded |
11-05-2022 |
All ESR Structures Work in progress. |
No file Uploaded |
11-05-2022 |
Clear water pipe line : Excavation and laying completed - 45 KM |
No file Uploaded |
11-05-2022 |
Distribution System : Excavation, Laying Completed 328 KM |
No file Uploaded |
11-05-2022 |
FHTC Completed 4125 Nos. |
No file Uploaded |
04-05-2022 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 14.8 KM- Hydro testing completed 8 KM |
No file Uploaded |
04-05-2022 |
Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house finishing work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab completed 6) wash water tank - 80% completed |
No file Uploaded |
04-05-2022 |
1) All CWR Structures work in progress. |
No file Uploaded |
04-05-2022 |
All ESR Structures Work in progress. |
No file Uploaded |
04-05-2022 |
Clear water pipe line : Excavation and laying completed - 45 KM |
No file Uploaded |
04-05-2022 |
Distribution System : Excavation, Laying Completed 312 KM |
No file Uploaded |
04-05-2022 |
FHTC Completed 3327 Nos. |
No file Uploaded |
27-04-2022 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 14.6 KM- Hydro testing completed 8 KM |
No file Uploaded |
27-04-2022 |
Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house finishing work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab completed 6) wash water tank - 80% completed |
No file Uploaded |
27-04-2022 |
1) All CWR Structures work in progress. |
No file Uploaded |
27-04-2022 |
All ESR Structures Work in progress. |
No file Uploaded |
27-04-2022 |
Clear water pipe line : Excavation and laying completed - 42 KM |
No file Uploaded |
27-04-2022 |
Distribution System : Excavation, Laying Completed 302 KM |
No file Uploaded |
27-04-2022 |
FHTC Completed 3327 Nos. |
No file Uploaded |
20-04-2022 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 14.6 KM- Hydro testing completed 8 KM |
No file Uploaded |
20-04-2022 |
Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house finishing work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab completed 6) wash water tank - 80% completed |
No file Uploaded |
20-04-2022 |
1) All CWR Structures work in progress. |
No file Uploaded |
20-04-2022 |
All ESR Structures Work in progress. |
No file Uploaded |
20-04-2022 |
Clear water pipe line : Excavation and laying completed - 42 KM |
No file Uploaded |
20-04-2022 |
Distribution System : Excavation, Laying Completed 297 KM |
No file Uploaded |
20-04-2022 |
FHTC Completed 3115 Nos. |
No file Uploaded |
13-04-2022 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 14.2 KM- Hydro testing completed 8 KM |
No file Uploaded |
13-04-2022 |
) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house finishing work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab completed 6) wash water tank - 80% completed |
No file Uploaded |
13-04-2022 |
1) All CWR Structures work in progress. |
No file Uploaded |
13-04-2022 |
All ESR Structures Work in progress. |
No file Uploaded |
13-04-2022 |
Clear water pipe line : Excavation and laying completed - 42 KM |
No file Uploaded |
13-04-2022 |
Distribution System : Excavation, Laying Completed 286 KM |
No file Uploaded |
13-04-2022 |
FHTC Completed 2470 Nos. |
No file Uploaded |
06-04-2022 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 14.2 KM- Hydro testing completed 8 KM |
No file Uploaded |
06-04-2022 |
) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house finishing work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab completed 6) wash water tank - 80% completed |
No file Uploaded |
06-04-2022 |
1) All CWR Structures work in progress. |
No file Uploaded |
06-04-2022 |
All ESR Structures Work in progress. |
No file Uploaded |
06-04-2022 |
Distribution System : Excavation, Laying Completed 277 KM |
No file Uploaded |
06-04-2022 |
Clear water pipe line : Excavation and laying completed - 40 KM |
No file Uploaded |
06-04-2022 |
FHTC Completed 2400 Nos. |
No file Uploaded |
02-04-2022 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 14.2 KM- Hydro testing completed 8 KM |
No file Uploaded |
02-04-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house finishing work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab completed 6) wash water tank - 80% completed |
No file Uploaded |
02-04-2022 |
Clear water pipe line : Excavation and laying completed - 40 KM |
No file Uploaded |
02-04-2022 |
Distribution System : Excavation, Laying Completed 265 KM |
No file Uploaded |
02-04-2022 |
1) Work in progress at CWR-01, CWR 2 CWR 03, CWR 04 ,CWR 6 & CWR -07 |
No file Uploaded |
02-04-2022 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
30-03-2022 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 14.2 KM- Hydro testing completed 8 KM |
No file Uploaded |
30-03-2022 |
Clear water pipe line : Excavation and laying completed - 40 KM |
No file Uploaded |
30-03-2022 |
Distribution System : Excavation, Laying Completed 265 KM |
No file Uploaded |
30-03-2022 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
30-03-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house finishing work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab completed 6) wash water tank - 80% completed |
No file Uploaded |
23-03-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house finishing work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab completed 6) wash water tank - 80% completed |
No file Uploaded |
23-03-2022 |
Clear water pipe line : Excavation and laying completed - 38 KM |
No file Uploaded |
23-03-2022 |
Distribution System : Excavation, Laying Completed 244 KM |
No file Uploaded |
23-03-2022 |
1) Work in progress at CWR-01, CWR 2 CWR 03, CWR 04 ,CWR 6 & CWR -07 |
No file Uploaded |
23-03-2022 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
23-03-2022 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 14 KM- Hydro testing completed 8 KM |
No file Uploaded |
09-03-2022 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 14 KM- Hydro testing completed 6.5 KM |
No file Uploaded |
09-03-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Plastering work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab work in progress 6) wash water tank - 80% completed |
No file Uploaded |
09-03-2022 |
Clear water pipe line : Excavation and laying completed - 38 KM |
No file Uploaded |
09-03-2022 |
1) Work in progress at CWR-01, CWR 2 CWR 03, CWR 04 ,CWR 5 & CWR -06 |
No file Uploaded |
09-03-2022 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
09-03-2022 |
Distribution System : Excavation, Laying Completed 145 KM |
No file Uploaded |
02-03-2022 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 14 KM- Hydro testing completed 6.5 KM |
No file Uploaded |
02-03-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Plastering work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab work in progress 6) wash water tank - 80% completed |
No file Uploaded |
02-03-2022 |
Clear water pipe line : Excavation and laying completed - 38 KM |
No file Uploaded |
02-03-2022 |
Distribution System : Excavation, Laying Completed 156 KM |
No file Uploaded |
02-03-2022 |
1) Work in progress at CWR-01, CWR 2 CWR 03, CWR 04 ,CWR 5 & CWR -06 |
No file Uploaded |
02-03-2022 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
23-02-2022 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 14 KM- Hydro testing completed 6.5 KM |
No file Uploaded |
23-02-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Plastering work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab work in progress 6) wash water tank - 80% completed |
No file Uploaded |
23-02-2022 |
1) Work in progress at CWR-01, CWR 2 CWR 03, CWR 04 ,CWR 5 & CWR -06 |
No file Uploaded |
23-02-2022 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
23-02-2022 |
Clear water pipe line : Excavation and laying completed - 38 KM |
No file Uploaded |
23-02-2022 |
Distribution System : Excavation, Laying Completed 138 KM |
No file Uploaded |
14-02-2022 |
1) Work in progress at CWR-01, CWR 2 CWR 03, CWR 04 ,CWR 5 & CWR -06
|
No file Uploaded |
14-02-2022 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12
|
No file Uploaded |
12-02-2022 |
1) Work in progress at CWR-01, CWR 2 CWR 03, CWR 04 ,CWR 5 & CWR -06
|
No file Uploaded |
12-02-2022 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12
|
No file Uploaded |
09-02-2022 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 13.5 KM- Hydro testing completed 6.5 KM |
No file Uploaded |
09-02-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Plastering work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab work in progress |
No file Uploaded |
09-02-2022 |
Clear water pipe line : Excavation and laying completed - 38 KM |
No file Uploaded |
09-02-2022 |
Distribution System : Completed 136 KM in Zone 11 , Zone 12 & Zone 10 , |
No file Uploaded |
09-02-2022 |
1) Work in progress at CWR-01, CWR 2 CWR 03, CWR 04 ,CWR 5 & CWR -06 |
No file Uploaded |
09-02-2022 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
09-02-2022 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 13.5 KM- Hydro testing completed 6.5 KM |
No file Uploaded |
02-02-2022 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 14 KM- Hydro testing completed 6.5 KM |
No file Uploaded |
02-02-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Plastering work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab work in progress |
No file Uploaded |
02-02-2022 |
Clear water pipe line : Excavation and laying completed - 38 KM |
No file Uploaded |
02-02-2022 |
Distribution System : Completed 136 KM in Zone 11 , Zone 12 & Zone 10 , |
No file Uploaded |
02-02-2022 |
1) Work in progress at CWR-01, CWR 2 CWR 03, CWR 04 ,CWR 5 & CWR -06 |
No file Uploaded |
02-02-2022 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
02-02-2022 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 3.5 KM |
No file Uploaded |
25-01-2022 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 13.5 KM- Hydro testing completed 6.5 KM |
No file Uploaded |
25-01-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Plastering work in progress 4) Clari flocculator 70 % completed- 5) Filter beds up to walkway completed |
No file Uploaded |
25-01-2022 |
Clear water pipe line : Excavation and laying completed - 38 KM |
No file Uploaded |
25-01-2022 |
Distribution System : Completed 134 KM in Zone 11 , Zone 12 & Zone 10 , |
No file Uploaded |
25-01-2022 |
1) Work in progress at CWR-01, CWR 2 CWR 03, CWR 04 ,CWR 5 & CWR -06 |
No file Uploaded |
25-01-2022 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
19-01-2022 |
Intake well: 15 th lift in progress - Switch yard - Columns up to 1 st brace beam completed |
No file Uploaded |
19-01-2022 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 13.5 KM- Hydro testing completed 6.5 KM |
No file Uploaded |
19-01-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Plastering work in progress 4) Clari flocculator 70 % completed- 5) Filter beds up to walkway completed |
No file Uploaded |
19-01-2022 |
Clear water pipe line : Excavation and laying completed - 38 KM |
No file Uploaded |
19-01-2022 |
Distribution System : Completed 136 KM in Zone 11 , Zone 12 & Zone 10 , |
No file Uploaded |
19-01-2022 |
1) Work in progress at CWR-01, CWR 2 CWR 03, CWR 04 ,CWR 5 & CWR -06 |
No file Uploaded |
19-01-2022 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
12-01-2022 |
Intake well: 13 th lift in progress - Switch yard - Columns up to 1 st brace beam completed |
No file Uploaded |
12-01-2022 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 13.5 KM- Hydro testing completed 6.5 KM |
No file Uploaded |
12-01-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Plastering work in progress 4) Clari flocculator 70 % completed- 5) Filter beds up to walkway completed |
No file Uploaded |
12-01-2022 |
Clear water pipe line : Excavation and laying completed - 38 KM |
No file Uploaded |
12-01-2022 |
Distribution System : Completed 134 KM in Zone 11 , Zone 12 & Zone 10 , |
No file Uploaded |
12-01-2022 |
1) Work in progress at CWR-01, CWR 2 CWR 03, CWR 04 ,CWR 5 & CWR -06 |
No file Uploaded |
12-01-2022 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
29-12-2021 |
Intake well: 10 th lift in progress - Switch yard - Plinth beam completed |
No file Uploaded |
29-12-2021 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 13.5 KM- Hydro testing completed 6.5 KM |
No file Uploaded |
29-12-2021 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Plastering work in progress 4) Clari flocculator Outer Launder in progress - 5) Filter beds up to walkway completed |
No file Uploaded |
29-12-2021 |
Clear water pipe line : Excavation and laying completed - 38 KM |
No file Uploaded |
29-12-2021 |
Distribution System : Completed 120 KM in Zone 11 , Zone 12 & Zone 10 , |
No file Uploaded |
29-12-2021 |
1) Work in progress at CWR-01, CWR 2 CWR 03, CWR 04 ,CWR 5 & CWR -06 |
No file Uploaded |
29-12-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
22-12-2021 |
Intake well: 9 th lift in progress - Switch yard - Plinth beam reinforcement in progress |
No file Uploaded |
22-12-2021 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 13.5 KM- Hydro testing completed 5.9 KM |
No file Uploaded |
22-12-2021 |
1) Aerator- Completed 90 % 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Brick work in progress 4) Clari flocculator Outer wall concrete 70% completed - 5) Filter beds up to walkway completed |
No file Uploaded |
22-12-2021 |
Clear water pipe line : Excavation and laying completed - 38 KM |
No file Uploaded |
22-12-2021 |
Distribution System : Completed 115 KM in Zone 11 , Zone 12 & Zone 10 , |
No file Uploaded |
22-12-2021 |
1) Work in progress at CWR-01, CWR 2 CWR 03, CWR 04 ,CWR 5 & CWR -06 |
No file Uploaded |
22-12-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
15-12-2021 |
Intake well: 7 th lift in progresss - Switch yard - Columns in progress |
No file Uploaded |
15-12-2021 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 13 .2 KM |
No file Uploaded |
15-12-2021 |
1) Aerator- Completed 90 % 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Brick work in progress 4) Clari flocculator Outer wall concrete 70% completed - 5) Filter beds up to walkway completed |
No file Uploaded |
15-12-2021 |
Clear water pipe line : Excavation and laying completed - 84 KM |
No file Uploaded |
15-12-2021 |
Distribution System : Completed 102 KM in Zone 11 , Zone 12 & Zone 10 , |
No file Uploaded |
15-12-2021 |
1) Work in progress at CWR-01, CWR -02 CWR -03, CWR 04 ,CWR 5 & CWR-06 |
No file Uploaded |
15-12-2021 |
Work in progress at ESR -01,ESR 04, ESR-03ESR -05,ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
08-12-2021 |
Intake well: 5 th lift Completed - Switch yard - Columns in progress |
No file Uploaded |
08-12-2021 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 13 .2 KM |
No file Uploaded |
08-12-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house -Brick work in progress 4) Clariflocculator Outer wall 2 nd lift concrete completed 5) Filter beds up to walk way completed - Side walls in progress 6) Wash water tank up to 2 nd brace beam completed |
No file Uploaded |
08-12-2021 |
Clear water pipe line : Excavation and laying completed - 38 KM |
No file Uploaded |
08-12-2021 |
Distribution System : Completed 93 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
08-12-2021 |
1) Work in progress at CWR-01, CWR -02 CWR -03, CWR 04 ,CWR 5 & CWR-06 |
No file Uploaded |
08-12-2021 |
Work in progress at ESR -01,ESR 04, ESR-03ESR -05,ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
01-12-2021 |
Intake well: 5 th lift in progress - Switch yard - Footings completed - Column reinforcement in progress completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
01-12-2021 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 13 KM |
No file Uploaded |
01-12-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house roof completed 4) Clariflocculator Outer wall 2 nd lift concrete completed 5) Filter beds up to walk way completed - Side walls in progress 6) Wash water tank up to 2 nd brace beam completed |
No file Uploaded |
01-12-2021 |
Clear water pipe line : Excavation and laying completed - 38 KM |
No file Uploaded |
01-12-2021 |
Distribution System : Completed 86 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
01-12-2021 |
1) Work in progress at CWR-01, CWR -02 CWR -03, CWR 04 ,CWR 5 & CWR-06 |
No file Uploaded |
01-12-2021 |
Work in progress at ESR -01,ESR 04, ESR-03ESR -05,ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
11-11-2021 |
Intake well: 4 th lift in progress - Switch yard - Footings completed - Column reinforcement in progress completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
11-11-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date 11.75 KM |
No file Uploaded |
11-11-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house up to roof level completed 4) Clariflocculator Raft in progress ,Outer wall 1 st lift concrete completed 5) Filter beds 2 nos Bottom raft completed - Side walls in progress 6) Wash water tank up to 1 st brace beam completed |
No file Uploaded |
11-11-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house up to roof level completed 4) Clariflocculator Raft in progress ,Outer wall 1 st lift concrete completed 5) Filter beds 2 nos Bottom raft completed - Side walls in progress 6) Wash water tank up to 1 st brace beam completed |
No file Uploaded |
11-11-2021 |
Clear water pipe line : Excavation and laying completed - 27 KM |
No file Uploaded |
11-11-2021 |
Distribution System : Completed 54 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
11-11-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
11-11-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
10-11-2021 |
Intake well: 4 th lift in progress - Switch yard - Footings completed - Column reinforcement in progress completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
10-11-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date 11.75 KM |
No file Uploaded |
10-11-2021 |
Hydro testing for raw water Pipe line or a length of 5.9 KM completed. |
No file Uploaded |
10-11-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house up to roof level completed 4) Clariflocculator Raft in progress ,Outer wall 1 st lift concrete completed 5) Filter beds 2 nos Bottom raft completed - Side walls in progress 6) Wash water tank up to 1 st brace beam completed |
No file Uploaded |
10-11-2021 |
Clear water pipe line : Excavation and laying completed - 27 KM |
No file Uploaded |
10-11-2021 |
Distribution System : Completed 40 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
10-11-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
10-11-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
08-11-2021 |
Intake well: 3 nd lift concrete completed - Switch yard - Footings completed - Column reinforcement in progress completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
08-11-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date 11.75 KM |
No file Uploaded |
08-11-2021 |
Hydro testing for raw water Pipe line or a length of 5.9 KM completed. |
No file Uploaded |
08-11-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house up to roof level completed 4) Clariflocculator Raft in progress ,Outer wall 1 st lift concrete completed 5) Filter beds 2 nos Bottom raft completed - Side walls in progress 6) Wash water tank up to 1 st brace beam completed |
No file Uploaded |
08-11-2021 |
Clear water pipe line : Excavation and laying completed - 27 KM |
No file Uploaded |
08-11-2021 |
Distribution System : Completed 40 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
08-11-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
08-11-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
27-10-2021 |
Intake well: 2 nd lift concrete completed - Switch yard - Footings completed - Column reinforcement in progress completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
27-10-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date 11.75 KM |
No file Uploaded |
27-10-2021 |
Hydro testing for raw water Pipe line or a length of 5.9 KM completed. |
No file Uploaded |
27-10-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house up to roof level completed 4) Clariflocculator Raft in progress ,Outer wall 1 st lift concrete completed 5) Filter beds 2 nos Bottom raft completed - Side walls in progress 6) Wash water tank up to 1 st brace beam completed |
No file Uploaded |
27-10-2021 |
Clear water pipe line : Excavation and laying completed - 26 KM |
No file Uploaded |
27-10-2021 |
Distribution System : Completed 37 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
27-10-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
27-10-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
26-10-2021 |
Intake well: 2 nd lift concrete completed - Switch yard - Footings completed - Column reinforcement in progress completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
26-10-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date 11.75 KM |
No file Uploaded |
26-10-2021 |
Hydro testing for raw water Pipe line or a length of 5.9 KM completed. |
No file Uploaded |
26-10-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house up to roof level completed 4) Clariflocculator Raft in progress ,Outer wall 1 st lift concrete completed 5) Filter beds 2 nos Bottom raft completed - Side walls in progress 6) Wash water tank up to 1 st brace beam completed |
No file Uploaded |
26-10-2021 |
Clear water pipe line : Excavation and laying completed - 25 KM |
No file Uploaded |
26-10-2021 |
Distribution System : Completed 35 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
26-10-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
26-10-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
20-10-2021 |
Intake well: 1 st concrete completed - Switch yard - Footings completed - Column reinforcement in progress completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
20-10-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date 11.75 KM |
No file Uploaded |
20-10-2021 |
Hydro testing for raw water Pipe line or a length of 5.9 KM completed. |
No file Uploaded |
20-10-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house up to roof level completed 4) Clariflocculator Raft in progress ,Outer wall 1 st lift concrete completed 5) Filter beds 2 nos Bottom raft completed - Side walls in progress 6) Wash water tank up to 1 st brace beam completed |
No file Uploaded |
20-10-2021 |
Clear water pipe line : Excavation and laying completed - 21 KM |
No file Uploaded |
20-10-2021 |
Distribution System : Completed 35 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
20-10-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
20-10-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
19-10-2021 |
Intake well: 1 st concrete completed - Switch yard - Footings completed - Column reinforcement in progress completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
19-10-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date 11.75 KM |
No file Uploaded |
19-10-2021 |
Hydro testing for raw water Pipe line or a length of 5.9 KM completed. |
No file Uploaded |
19-10-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house up to roof level completed 4) Clariflocculator Raft in progress ,Outer wall 1 st lift concrete completed 5) Filter beds 2 nos Bottom raft completed - Side walls in progress 6) Wash water tank up to 1 st brace beam completed |
No file Uploaded |
19-10-2021 |
Clear water pipe line : Excavation and laying completed - 21 KM |
No file Uploaded |
19-10-2021 |
Distribution System : Completed 35 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
19-10-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
19-10-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
18-10-2021 |
Intake well: 1 st concrete completed - Switch yard - Footings completed - Column reinforcement in progress completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
18-10-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date 11.75 KM |
No file Uploaded |
18-10-2021 |
Hydro testing for raw water Pipe line or a length of 5.9 KM completed. |
No file Uploaded |
18-10-2021 |
Clear water pipe line : Excavation and laying completed - 20 KM |
No file Uploaded |
18-10-2021 |
Distribution System : Completed 35 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
18-10-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house up to roof level completed 4) Clariflocculator Raft in progress ,Outer wall 1 st lift concrete completed 5) Filter beds 2 nos Bottom raft completed - Side walls in progress 6) Wash water tank up to 1 st brace beam completed |
No file Uploaded |
18-10-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
18-10-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
16-10-2021 |
Intake well: 1 st concrete completed - Switch yard - Footings completed - Column reinforcement in progress completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
16-10-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date 11.75 KM |
No file Uploaded |
16-10-2021 |
Hydro testing for raw water Pipe line or a length of 5.9 KM completed. |
No file Uploaded |
16-10-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house up to roof level completed 4) Clariflocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed - Side walls in progress 6) Wash water tank up to plinth completed |
No file Uploaded |
16-10-2021 |
Clear water pipe line : Excavation and laying completed - 19 KM |
No file Uploaded |
16-10-2021 |
Distribution System : Completed 32 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
16-10-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
16-10-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
13-10-2021 |
Intake well: 1 st concrete completed - Switch yard - Footings completed - Column reinforcement in progress completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
13-10-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date 11.75 KM |
No file Uploaded |
13-10-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house up to roof level completed 4) Clariflocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed - Side walls in progress 6) Wash water tank up to plinth completed |
No file Uploaded |
13-10-2021 |
Clear water pipe line : Excavation and laying completed - 18.5 KM |
No file Uploaded |
13-10-2021 |
Distribution System : Completed 30 KM in Zone 10 , Zone 11 & Zone 12
|
No file Uploaded |
13-10-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
13-10-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
12-10-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date 11.75 KM |
No file Uploaded |
12-10-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house up to roof level completed 4) Clariflocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed - Side walls in progress 6) Wash water tank up to plinth completed |
No file Uploaded |
12-10-2021 |
Clear water pipe line : Excavation and laying completed - 18.5 KM |
No file Uploaded |
12-10-2021 |
Distribution System : Completed 28 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
12-10-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
12-10-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
11-10-2021 |
Intake well: 1 st concrete completed - Switch yard - Footings completed - Column reinforcement in progress completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
11-10-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date 11.75 KM |
No file Uploaded |
11-10-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house up to roof level completed 4) Clariflocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed - Side walls in progress 6) Wash water tank up to plinth completed |
No file Uploaded |
11-10-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
11-10-2021 |
Clear water pipe line : Excavation and laying completed - 18 KM |
No file Uploaded |
11-10-2021 |
Distribution System : Completed 27 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
11-10-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
11-10-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
11-10-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft completed out of 6 Nos |
No file Uploaded |
06-10-2021 |
Intake well: Raft completed- Switch yard - Foundation PCC completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
06-10-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date 11.75 KM |
No file Uploaded |
06-10-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house up to roof level completed 4) Clariflocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed - Side walls in progress 6) Wash water tank up to plinth completed |
No file Uploaded |
06-10-2021 |
Clear water pipe line : Excavation and laying completed - 15.5 KM |
No file Uploaded |
06-10-2021 |
Distribution System : Completed 25 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
06-10-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
06-10-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
05-10-2021 |
Intake well: Raft completed- Switch yard - Foundation PCC completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
05-10-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date 11.75 KM |
No file Uploaded |
05-10-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
05-10-2021 |
Clear water pipe line : Excavation and laying completed - 15 KM |
No file Uploaded |
05-10-2021 |
Distribution System : Completed 24 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
05-10-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house up to roof level completed 4) Clariflocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed - Side walls in progress 6) Wash water tank up to plinth completed |
No file Uploaded |
05-10-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
04-10-2021 |
Intake well: Raft completed- Switch yard - Foundation PCC completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
04-10-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date 11.75 KM |
No file Uploaded |
04-10-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house up to roof level completed 4) Clariflocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed - Side walls in progress 6) Wash water tank up to plinth completed |
No file Uploaded |
04-10-2021 |
Clear water pipe line : Excavation and laying completed - 14.5 KM |
No file Uploaded |
04-10-2021 |
Distribution System : Completed 23 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
04-10-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
04-10-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
04-10-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
29-09-2021 |
Intake well: Raft completed- Switch yard - Foundation PCC completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
29-09-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date is 11.7 KM |
No file Uploaded |
29-09-2021 |
Clear water pipe line : Excavation and laying completed - 8.0 KM |
No file Uploaded |
29-09-2021 |
Distribution System : Completed 13 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
29-09-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
29-09-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft completed out of 6 Nos |
No file Uploaded |
29-09-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
29-09-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
28-09-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date is 11.7 KM |
No file Uploaded |
28-09-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
28-09-2021 |
Clear water pipe line : Excavation and laying completed - 7.2 KM |
No file Uploaded |
28-09-2021 |
Distribution System : Completed 13 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
28-09-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house up to roof level completed 4) Clariflocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed - Side walls in progress 6) Wash water tank up to plinth completed |
No file Uploaded |
28-09-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
28-09-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
27-09-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date is 11.7 KM |
No file Uploaded |
27-09-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
27-09-2021 |
Clear water pipe line : Excavation and laying completed - 7.0KM |
No file Uploaded |
27-09-2021 |
Distribution System : Completed 12 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
27-09-2021 |
1) Aerator- 90 % completed 2 ) Flash mixers - completed 3) Chemical House & Chlorine house up to roof level completed 4) Clariflocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed - Side walls in progress 6) Wash water tank up to plinth completed |
No file Uploaded |
27-09-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
27-09-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
22-09-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date is 11.7 KM |
No file Uploaded |
22-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed 6) Wash water tank up to plinth completed |
No file Uploaded |
22-09-2021 |
Clear water pipe line : Excavation and laying completed - 5.6 KM |
No file Uploaded |
22-09-2021 |
Distribution System : Completed 7.5 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
22-09-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
22-09-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
22-09-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
21-09-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date is 11.7 KM |
No file Uploaded |
21-09-2021 |
Clear water pipe line : Excavation and laying completed - 5.5 KM |
No file Uploaded |
21-09-2021 |
Distribution System : Completed 7.0 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
21-09-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
21-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed 6) Wash water tank up to plinth completed |
No file Uploaded |
21-09-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
21-09-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
20-09-2021 |
Distribution System : Completed 6.0 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
20-09-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
20-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed 6) Wash water tank up to plinth completed |
No file Uploaded |
20-09-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
20-09-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
20-09-2021 |
Intake well: PCC Completed. Raft reinforcement work completed- Switch yard - Foundation PCC completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
20-09-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date is 11.5 KM |
No file Uploaded |
20-09-2021 |
Clear water pipe line : Excavation and laying completed - 5.0 KM |
No file Uploaded |
15-09-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date is 11.5 KM |
No file Uploaded |
15-09-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
15-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed 6) Wash water tank up to plinth completed |
No file Uploaded |
15-09-2021 |
Distribution System : Completed 5 KM in Zone 10 , Zone 11 & Zone 12 |
No file Uploaded |
15-09-2021 |
Clear water pipe line : Excavation and laying completed - 4.2 KM |
No file Uploaded |
15-09-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
15-09-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
14-09-2021 |
Intake well: PCC Completed. Raft reinforcement work in progress- Switch yard - Foundation PCC completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
14-09-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date is 11.2 KM |
No file Uploaded |
14-09-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
14-09-2021 |
Distribution System : Completed 4 KM in Zone 11 & Zone 12 |
No file Uploaded |
14-09-2021 |
Clear water pipe line : Excavation and laying completed - 4 KM |
No file Uploaded |
14-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed 6) Wash water tank up to plinth completed |
No file Uploaded |
14-09-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
14-09-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
13-09-2021 |
Intake well: PCC Completed. Raft reinforcement work in progress- Switch yard - Foundation PCC completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
13-09-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date is 11 KM |
No file Uploaded |
13-09-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
13-09-2021 |
Distribution System : Completed 3.5 KM in Zone 11 & Zone 12 |
No file Uploaded |
13-09-2021 |
Clear water pipe line : Excavation and laying completed - 3.5 KM |
No file Uploaded |
13-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed 6) Wash water tank up to plinth completed |
No file Uploaded |
13-09-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
13-09-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
12-09-2021 |
Intake well: PCC Completed. Raft reinforcement work in progress- Switch yard - Foundation PCC completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
12-09-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 11 KM |
No file Uploaded |
12-09-2021 |
1.DI Pipes 700 mm Dia. Received at Site 13 KM. 2. Laying of pipe line work commenced and completed as on date is 11 KM |
No file Uploaded |
12-09-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
12-09-2021 |
Distribution System : Completed 3 KM in Zone 11 & Zone 12 |
No file Uploaded |
12-09-2021 |
Clear water pipe line : Excavation and laying completed - 2.5 KM |
No file Uploaded |
12-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed 6) Wash water tank up to plinth completed |
No file Uploaded |
12-09-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
12-09-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
08-09-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 10.7 KM |
No file Uploaded |
08-09-2021 |
Clear water pipe line : Excavation and laying completed - 2.0 KM |
No file Uploaded |
08-09-2021 |
Distribution System : Completed 2.5 KM in Zone 11 & Zone 12 |
No file Uploaded |
08-09-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
08-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed 6) Wash water tank up to plinth completed |
No file Uploaded |
08-09-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
07-09-2021 |
Intake well: PCC Completed. Switch yard - Foundation PCC completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
07-09-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 10.5 KM |
No file Uploaded |
07-09-2021 |
Clear water pipe line : Excavation and laying completed - 1.8 KM |
No file Uploaded |
07-09-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
07-09-2021 |
Distribution System : Completed 2.3 KM in Zone 11 & Zone 12 |
No file Uploaded |
07-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed 6) Wash water tank up to plinth completed |
No file Uploaded |
07-09-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
07-09-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
06-09-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 10.5 KM |
No file Uploaded |
06-09-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
06-09-2021 |
Intake well: PCC Completed. Switch yard - Foundation PCC completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
06-09-2021 |
Clear water pipe line : Excavation and laying completed - 1,2 KM |
No file Uploaded |
06-09-2021 |
Distribution System : Completed 2.0 KM in Zone 11 & Zone 12 |
No file Uploaded |
06-09-2021 |
1) Aerator- Haft height structure completed
2 ) Raw water Channel ,Flash mixers - Haft height structure completed
3) Chemical House & Chlorine house up to lintel level completed
4) Clari flocculator Outer wall concrete completed - Inside PCC in progress
5) Filter beds Bottom raft completed 6) Wash water tank up to plinth completed |
No file Uploaded |
06-09-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
06-09-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
01-09-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 10 KM |
No file Uploaded |
01-09-2021 |
Clear water pipe line : Excavation and laying completed - 1.32 KM |
No file Uploaded |
01-09-2021 |
Distribution System : Completed 1.3 KM in Zone12 |
No file Uploaded |
01-09-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
01-09-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to half height structures completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall concrete completed - 4) Filter beds PCC completed- Bottom raft is in progress |
No file Uploaded |
01-09-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
01-09-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
31-08-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9.3 KM |
No file Uploaded |
31-08-2021 |
Clear water pipe line : Excavation and laying completed - 1.32 KM |
No file Uploaded |
31-08-2021 |
Distribution System : Completed 1.3 KM in Zone12 |
No file Uploaded |
31-08-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
31-08-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to half height structures completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall concrete completed - 4) Filter beds PCC completed- Bottom raft Reinforcement is in progress |
No file Uploaded |
31-08-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
30-08-2021 |
Intake well: PCC Completed. Switch yard , approach bridge and intake pipe line excavation in progress |
No file Uploaded |
30-08-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9.3 KM |
No file Uploaded |
30-08-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
30-08-2021 |
Clear water pipe line : Excavation and laying completed - 1.0 KM |
No file Uploaded |
30-08-2021 |
Distribution net work : Excavation and laying completed - 1.0 KM in Zone 12 |
No file Uploaded |
30-08-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to half height structures completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall concrete completed - 4) Filter beds PCC completed- Bottom raft Reinforcement is in progress |
No file Uploaded |
30-08-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
30-08-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
28-08-2021 |
Intake well: PCC Completed. Switch yard , approach bridge and intake pipe line excavation in progress |
No file Uploaded |
28-08-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
28-08-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
28-08-2021 |
Clear water pipe line : Excavation and laying completed - 0.8 KM |
No file Uploaded |
28-08-2021 |
Distribution System : Completed 0.8 KM in Zone 12 |
No file Uploaded |
28-08-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to half height structures completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall concrete completed - 4) Filter beds PCC completed- Bottom raft Reinforcement is in progress |
No file Uploaded |
28-08-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
25-08-2021 |
Intake well: Excavation Completed. Switch yard , approach bridge and intake pipe line excavation in progress |
No file Uploaded |
25-08-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
25-08-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
25-08-2021 |
Clear water pipe line : Excavation and laying completed - 1.0 KM |
No file Uploaded |
25-08-2021 |
Distribution pipe line : Excavation and laying completed - 1.0 KM |
No file Uploaded |
25-08-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to half height structures completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall concrete completed - 4) Filter beds PCC completed- Bottom raft Reinforcement is in progress |
No file Uploaded |
25-08-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
25-08-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
23-08-2021 |
Intake well: Excavation Completed. Switch yard , approach bridge and intake pipe line excavation in progress |
No file Uploaded |
23-08-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
23-08-2021 |
Hydro testing for raw water Pipe line or a length of 3.9 KM completed. |
No file Uploaded |
23-08-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to half height structures completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall concrete completed - 4) Filter beds PCC completed- Bottom raft Reinforcement is in progress |
No file Uploaded |
23-08-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
23-08-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
21-08-2021 |
Intake well: Excavation Completed. Switch yard , approach bridge and intake pipe line excavation in progress |
No file Uploaded |
21-08-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
21-08-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to half height structures completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall concrete completed - 4) Filter beds PCC completed- Bottom raft Reinforcement is in progress |
No file Uploaded |
21-08-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
21-08-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
17-08-2021 |
Intake well: Excavation Completed. Switch yard , approach bridge and intake pipe line excavation in progress |
No file Uploaded |
17-08-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
17-08-2021 |
Hydro testing for raw water Pipe line or a length of 4.0 KM completed. |
No file Uploaded |
17-08-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to half height structures completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall concrete completed - 4) Filter beds PCC completed- Bottom raft Reinforcement is in progress |
No file Uploaded |
17-08-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
17-08-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
16-08-2021 |
Intake well: Excavation Completed. Switch yard , approach bridge and intake pipe line excavation in progress |
No file Uploaded |
16-08-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
16-08-2021 |
Hydro testing for raw water Pipe line or a length of 3.3 KM completed. |
No file Uploaded |
16-08-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to half height structures completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall concrete completed - 4) Filter beds PCC completed- Bottom raft Reinforcement is in progress |
No file Uploaded |
16-08-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
16-08-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
11-08-2021 |
Intake well: Excavation Completed |
No file Uploaded |
11-08-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
11-08-2021 |
Hydro testing for raw water Pipe line or a length of 3.3 KM completed. |
No file Uploaded |
11-08-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to half height structures completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall concrete completed - 4) Filter beds PCC completed- Bottom raft Reinforcement is in progress |
No file Uploaded |
11-08-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
11-08-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
10-08-2021 |
Intake well: Survey, Soil testing and approach road and Excavation Completed |
No file Uploaded |
10-08-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
10-08-2021 |
Hydro testing for raw water Pipe line or a length of 3.3 KM completed. |
No file Uploaded |
10-08-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to half height structures completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall concrete completed - 4) Filter beds PCC completed- Bottom raft Reinforcement is in progress |
No file Uploaded |
10-08-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
10-08-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
10-08-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
09-08-2021 |
Intake well: Survey, Soil testing and approach road and Excavation Completed |
No file Uploaded |
09-08-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
09-08-2021 |
Hydro testing for raw water Pipe line or a length of 3.3 KM completed. |
No file Uploaded |
09-08-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to half height structures completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall concrete completed - 4) Filter beds PCC completed- Bottom raft Reinforcement is in progress |
No file Uploaded |
09-08-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 |
No file Uploaded |
09-08-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
04-08-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
04-08-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
04-08-2021 |
Hydro testing for raw water Pipe line or a length of 3.3 KM completed. |
No file Uploaded |
04-08-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to Plinth level completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall PCC completed - Reinforcement work in progress 4) Filter beds PCC completed |
No file Uploaded |
04-08-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
04-08-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
03-08-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
03-08-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
03-08-2021 |
Hydro testing for raw water Pipe line or a length of 3.3 KM completed. |
No file Uploaded |
03-08-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to Plinth level completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall PCC completed - Reinforcement work in progress 4) Filter beds PCC completed |
No file Uploaded |
03-08-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 04 ,CWR 5 & CWR-06 |
No file Uploaded |
03-08-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
02-08-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
02-08-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
02-08-2021 |
Hydro testing for raw water Pipe line or a length of 3.3 KM completed. |
No file Uploaded |
02-08-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to Plinth level completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall PCC completed - Reinforcement work in progress 4) Filter beds Excavation completed |
No file Uploaded |
02-08-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
02-08-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
29-07-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
29-07-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
29-07-2021 |
Hydro testing for raw water Pipe line or a length of 1.9 KM completed. 2 nd reach around 1.4 Km is in progress |
No file Uploaded |
29-07-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to Plinth level completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall PCC completed - Reinforcement work in progress 4) Filter beds Excavation completed |
No file Uploaded |
28-07-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
28-07-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
28-07-2021 |
Hydro testing for raw water Pipe line or a length of 1.9 KM completed. 2 nd reach around 1.4 Km is in progress |
No file Uploaded |
28-07-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to Plinth level completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall PCC completed - Reinforcement work in progress 4) Filter beds Excavation completed |
No file Uploaded |
28-07-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
28-07-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
27-07-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
27-07-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
27-07-2021 |
Hydro testing for raw water Pipe line or a length of 1.9 KM completed. 2 nd reach around 1.4 Km is in progress |
No file Uploaded |
27-07-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to Plinth level completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall PCC completed - Reinforcement work in progress 4) Filter beds Excavation completed |
No file Uploaded |
27-07-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
27-07-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
26-07-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
26-07-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
26-07-2021 |
Hydro testing for raw water Pipe line or a length of 1.9 KM completed. |
No file Uploaded |
26-07-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to Plinth level completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall PCC completed - Reinforcement work in progress 4) Filter beds Excavation completed |
No file Uploaded |
26-07-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
26-07-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
24-07-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
24-07-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
24-07-2021 |
Hydro testing for raw water Pipe line or a length of 1.9 KM completed. Another reach around 1.4 KM Hydro testing in progress |
No file Uploaded |
24-07-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to Plinth level completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall PCC completed - Reinforcement work in progress 4) Filter beds Excavation completed |
No file Uploaded |
24-07-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
24-07-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
21-07-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress- completed 80% |
No file Uploaded |
21-07-2021 |
1.DI Pipes 700 mm Dia. Received at Site 8.9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
21-07-2021 |
Hydro testing for raw water Pipe line or a length of 1.9 KM completed. Another reach around 1.4 KM Hydro testing in progress |
No file Uploaded |
21-07-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to Plinth level completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall PCC completed - Reinforcemnt work in progress 4) Filter beds Excavation completed |
No file Uploaded |
21-07-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
21-07-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 9, CWR 10 & CWR 11 |
No file Uploaded |
20-07-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
20-07-2021 |
1.DI Pipes 700 mm Dia. Received at Site 8.9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
20-07-2021 |
Hydro testing for raw water Pipe line or a length of 1.9 KM completed. Another reach around 1.4 KM Hydro testing in progress |
No file Uploaded |
20-07-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to Plinth level completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall PCC completed - Reinforcemnt work in progress 4) Filter beds Excavation completed |
No file Uploaded |
20-07-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
20-07-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
19-07-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
19-07-2021 |
1.DI Pipes 700 mm Dia. Received at Site 8.9 KM. 2. Laying of pipe line work commenced and completed as on date is 9 KM |
No file Uploaded |
19-07-2021 |
Hydro testing for raw water Pipe line or a length of 1.9 KM completed. |
No file Uploaded |
19-07-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to Plinth level completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall PCC completed - Reinforcemnt work in progress 4) Filter beds Excavation completed |
No file Uploaded |
19-07-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
19-07-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
16-07-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
16-07-2021 |
1.DI Pipes 700 mm Dia. Received at Site 8.9 KM. 2. Laying of pipe line work commenced and completed as on date is 8.7 KM |
No file Uploaded |
16-07-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to Plinth level completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall PCC completed - Reinforcemnt work in progress 4) Filter beds Excavation completed |
No file Uploaded |
16-07-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
16-07-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
14-07-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
14-07-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 9.0 KM |
No file Uploaded |
14-07-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to Plinth level completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall PCC completed - Reinforcemnt work in progress 4) Filter beds Excavation completed |
No file Uploaded |
14-07-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
14-07-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
13-07-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
13-07-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 9.0 KM |
No file Uploaded |
13-07-2021 |
Hydro testing for raw water Pipe line or a length of 1.9 KM completed. |
No file Uploaded |
13-07-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to Plinth level completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall PCC completed - Reinforcemnt work in progress 4) Filter beds Excavation completed |
No file Uploaded |
13-07-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
13-07-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
12-07-2021 |
Hydro testing for raw water Pipe line or a length of 1.9 KM completed. |
No file Uploaded |
12-07-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to Plinth level completed -2) Chemical House & Chlorine house up to lintle level completed 3) Clari flocculator Outer wall PCC completed - Reinforcemnt work in progress 4) Filter beds Excavation completed |
No file Uploaded |
12-07-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
12-07-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
12-07-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
12-07-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 8.5 KM |
No file Uploaded |
07-07-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
07-07-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 7.7 KM |
No file Uploaded |
07-07-2021 |
Hydro testing for raw water Pipe line or a length of 1.9 KM completed. |
No file Uploaded |
07-07-2021 |
1) PCC completed all structures except Clariflocculator and CWR +PH 2) Aerator, Raw water Channel Flash mixers , Chemical house and chlorine house Up to Plinth level completed - |
No file Uploaded |
07-07-2021 |
1) Work in progress at CWR-01, CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
07-07-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
06-07-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
06-07-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 7.7 KM |
No file Uploaded |
06-07-2021 |
Hydro testing for raw water Pipe line or a length of 1.9 KM completed. |
No file Uploaded |
06-07-2021 |
1) PCC completed all structures except Clariflocculator and CWR +PH 2) Aerator, Raw water Channel Flash mixers , Chemical house and chlorine house Up to Plinth level completed - |
No file Uploaded |
06-07-2021 |
1) Work in progress at CWR-01,CWR 2 , CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
06-07-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
05-07-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
05-07-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 7.7 KM |
No file Uploaded |
05-07-2021 |
Hydro testing for raw water Pipe line or a length of 1.9 KM completed. |
No file Uploaded |
05-07-2021 |
1) PCC completed all structures except Clariflocculator and CWR +PH 2) Aerator, Raw water Channel Flash mixers , Chemical house and chlorine house Up to Plinth level completed - |
No file Uploaded |
05-07-2021 |
1) Work in progress at CWR-01,CWR 2 , CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
05-07-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
01-07-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
01-07-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 7.2 KM |
No file Uploaded |
01-07-2021 |
1) PCC completed all structures except Clariflocculator and CWR +PH 2) Aerator, Raw water Channel Flash mixers , Chemical house and chlorine house Up to Plinth level completed - |
No file Uploaded |
01-07-2021 |
1) Work in progress at CWR-01,CWR 2 , CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
01-07-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
30-06-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
30-06-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 7.2 KM |
No file Uploaded |
30-06-2021 |
1) PCC completed all structures except Clariflocculator and CWR +PH 2) Aerator, Raw water Channel Flash mixers , Chemical house and chlorine house Up to Plinth level completed - |
No file Uploaded |
30-06-2021 |
1) Work in progress at CWR-01,CWR 2 , CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
30-06-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
29-06-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
29-06-2021 |
1) PCC completed all structures except Clariflocculator and CWR +PH
2) Aerator, Raw water Channel Flash mixers , Chemical house and chlorine house Up to Plinth level completed - |
No file Uploaded |
29-06-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 7.1 KM |
No file Uploaded |
29-06-2021 |
1) Work in progress at CWR-01,CWR 2 , CWR 03, CWR 05 ,CWR 6 & CWR-07 |
No file Uploaded |
29-06-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
28-06-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
28-06-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 7.1 KM |
No file Uploaded |
28-06-2021 |
1) PCC completed all structures except Clariflocculator and CWR +PH 2) Aerator, Raw water Channel Flash mixers , Chemical house and chlorine house Up to Plinth level completed - |
No file Uploaded |
28-06-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 05 CWR 6 & CWR 07 |
No file Uploaded |
28-06-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
25-06-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
25-06-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 6.9 KM |
No file Uploaded |
25-06-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 05 and CWR 6 |
No file Uploaded |
25-06-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
23-06-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
23-06-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 6.7 KM |
No file Uploaded |
23-06-2021 |
1) PCC completed all structures except Clari flocculator and CWR +PH 2) Aerator, Raw water Channel Flash mixers , Chemical house and chlorine house Up to Plinth level completed -3) Filter beds raft reinforcement work in progress |
No file Uploaded |
23-06-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 05 and CWR 6 |
No file Uploaded |
23-06-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
22-06-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
22-06-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 6.6 KM |
No file Uploaded |
22-06-2021 |
1) PCC completed all structures except Clariflocculator and CWR +PH
2) Aerator, Raw water Channel Flash mixers , Chemical house and chlorine house Up to Plinth level completed - |
No file Uploaded |
22-06-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 05 and CWR 6 |
No file Uploaded |
22-06-2021 |
Work in progress at ESR -03,ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
21-06-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
21-06-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 6.5 KM |
No file Uploaded |
21-06-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 05 and CWR 6 |
No file Uploaded |
21-06-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
16-06-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
16-06-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 5.7 KM |
No file Uploaded |
16-06-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress 4) Aerator central raft and Column footings completed at Chemical House and Chlorine house |
No file Uploaded |
16-06-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Work in progress at CWR-01,CWR 3 and CWR 5 |
No file Uploaded |
16-06-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
15-06-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
15-06-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 5.5 KM |
No file Uploaded |
15-06-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress 4) Aerator central raft and Column footings completed at Chemical House and Chlorine house |
No file Uploaded |
15-06-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Work in progress at CWR-01,CWR 3 and CWR 5 |
No file Uploaded |
15-06-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
13-06-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
13-06-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 5.5 KM |
No file Uploaded |
13-06-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress 4) Aerator central raft and Column footings completed at Chemical House and Chlorine house |
No file Uploaded |
13-06-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Work in progress at CWR-01,CWR 3 and CWR 5 |
No file Uploaded |
13-06-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
09-06-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
09-06-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 5.0 KM |
No file Uploaded |
09-06-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed
3) Wash water tank excavation in progress
4) Aerator central raft and Column footings completed at Chemical House and |
No file Uploaded |
09-06-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Work in progress at CWR-01,CWR 3 and CWR 5 |
No file Uploaded |
09-06-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
08-06-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
08-06-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 4.5 KM |
No file Uploaded |
08-06-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Work in progress at CWR-01,CWR 3 and CWR 5 |
No file Uploaded |
08-06-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
08-06-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress 4) Reinforcement work in progress at Chemical House and Chlorine house |
No file Uploaded |
04-06-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
04-06-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 4.5 KM |
No file Uploaded |
04-06-2021 |
1) Excavation completed - all structures 2) PCC completed all structures except Clariflocculator and CWR +PH 3) RCC footings completed -Aerator ,Chemical house and chlorine House |
No file Uploaded |
04-06-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Work in progress at CWR-01,CWR 3 and CWR 5 |
No file Uploaded |
04-06-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
02-06-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
02-06-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 4.2 KM |
No file Uploaded |
02-06-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Work in progress at CWR-01,CWR 3 and CWR 5 |
No file Uploaded |
02-06-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
01-06-2021 |
Intake well: Survey, Soil testing and approach road completed. Excavation work in progress |
No file Uploaded |
01-06-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 4.2 KM |
No file Uploaded |
01-06-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress 4) Reinforcement work in progress at Chemical House and Chlorine house |
No file Uploaded |
01-06-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Work in progress at CWR-01,CWR 3 and CWR 5 |
No file Uploaded |
01-06-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
31-05-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
31-05-2021 |
Intake well: Survey, Soil testing and approach road completed |
No file Uploaded |
31-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 4.2 KM |
No file Uploaded |
31-05-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed.
2) Excavation for Filter house Completed
3) Wash water tank excavation in progress
4) Reinforcement work in progress at Chemical House and Chlorine house |
No file Uploaded |
31-05-2021 |
1) Soil testing completed at all 7 CWRs Location.
2) Work in progress at CWR-01,CWR 3 and CWR 5 |
No file Uploaded |
26-05-2021 |
Intake well: Survey, Soil testing and approach road completed |
No file Uploaded |
26-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
26-05-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress 4) Reinforcement work in progress at Chemical House and Chlorine house |
No file Uploaded |
26-05-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Work in progress at CWR-01,CWR 3 and CWR 5 |
No file Uploaded |
26-05-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
25-05-2021 |
Intake well: Survey, Soil testing and approach road completed |
No file Uploaded |
25-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 9.6 KM.
2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
25-05-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress 4) Reinforcement work in progress at Chemical House and Chlorine house |
No file Uploaded |
25-05-2021 |
1) Soil testing completed at all 7 CWRs Location.
2) Work in progress at CWR-01,CWR 3 and CWR 5 |
No file Uploaded |
25-05-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
24-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
24-05-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress 4) Reinforcement work in progress at Chemical House and Chlorine house |
No file Uploaded |
24-05-2021 |
Intake well: Survey, Soil testing and approach road completed |
No file Uploaded |
24-05-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at , CWR 2.
3) Work in progress at CWR-01,CWR 3 and CWR 5 |
No file Uploaded |
24-05-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
19-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
19-05-2021 |
Intake well: Survey, Soil testing and approach road completed |
No file Uploaded |
19-05-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress 4) Reinforcement work in progress at Chemical House and Chlorine house |
No file Uploaded |
19-05-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR-01,CWR 3 and CWR 5. |
No file Uploaded |
19-05-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
18-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
18-05-2021 |
Intake well: Survey, Soil testing and approach road completed |
No file Uploaded |
18-05-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress 4) Reinforcement work in progress at Chemical House and Chlorine house |
No file Uploaded |
18-05-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR-01,CWR 3 and CWR 5. |
No file Uploaded |
18-05-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
17-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
17-05-2021 |
Intake well: Survey, Soil testing and approach road completed |
No file Uploaded |
17-05-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress 4) Reinforcement work in progress at Chemical House and Chlorine house |
No file Uploaded |
17-05-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR-01,CWR 3 and CWR 5. |
No file Uploaded |
17-05-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
15-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
15-05-2021 |
Intake well: Survey, Soil testing and approach road completed |
No file Uploaded |
15-05-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress 4) Reinforcement work in progress at Chemical House and Chlorine house |
No file Uploaded |
15-05-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR-01,CWR 3 and CWR 5. |
No file Uploaded |
15-05-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 04, ESR 06 , ESR 08 , ESR 11 & ESR 12. |
No file Uploaded |
14-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
14-05-2021 |
Intake well: Survey, Soil testing and approach road completed |
No file Uploaded |
14-05-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress 4) Reinforcement work in progress at Chemical House and Chlorine house |
No file Uploaded |
14-05-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR-02,CWR 3 and CWR 5. |
No file Uploaded |
14-05-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11. |
No file Uploaded |
14-05-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11. |
No file Uploaded |
13-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
13-05-2021 |
Intake well:
Survey , soil testing and approach road completed |
No file Uploaded |
13-05-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress 4) Reinforcement work in progress at Chemical House and Chlorine house |
No file Uploaded |
13-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
13-05-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
13-05-2021 |
1) Soil testing completed at 12 Locations. 2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ,ESR 10 ESR 11 & ESR 12 |
No file Uploaded |
12-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
12-05-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress 4) Reinforcement work in progress at Chemical House and Chlorine house |
No file Uploaded |
12-05-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
12-05-2021 |
1) Soil testing completed at 12 Locations. 2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ,ESR 10 & ESR 11 & ESR 12 |
No file Uploaded |
11-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
11-05-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress 4) Reinforcement work in progress at Chemical House and Chlorine house |
No file Uploaded |
11-05-2021 |
1) Soil testing completed at 12 Locations. 2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ,ESR 10 & ESR 11 & ESR 12 |
No file Uploaded |
10-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
10-05-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
10-05-2021 |
1) Soil testing completed at 12 Locations. 2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ,ESR 10 & ESR 11. |
No file Uploaded |
07-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
07-05-2021 |
) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress 4) Reinforcement work in progress at Chemical House and Chlorine house |
No file Uploaded |
07-05-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
07-05-2021 |
1) Soil testing completed at 12 Locations. 2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ,ESR 10 & ESR 11. |
No file Uploaded |
06-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
06-05-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress |
No file Uploaded |
06-05-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
06-05-2021 |
1) Soil testing completed at 12 Locations. 2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ,ESR 10 & ESR 11. |
No file Uploaded |
05-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
05-05-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress |
No file Uploaded |
05-05-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
05-05-2021 |
1) Soil testing completed at 12 Locations. 2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ,ESR 10 & ESR 11. |
No file Uploaded |
04-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
04-05-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed 3) Wash water tank excavation in progress |
No file Uploaded |
04-05-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
04-05-2021 |
1) Soil testing completed at 12 Locations. 2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ,ESR 10 & ESR 11. |
No file Uploaded |
03-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM.
2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
03-05-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed |
No file Uploaded |
03-05-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
03-05-2021 |
1) Soil testing completed at 12 Locations. 2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ,ESR 10 & ESR 11. |
No file Uploaded |
01-05-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
01-05-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed |
No file Uploaded |
01-05-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
01-05-2021 |
1) Soil testing completed at 12 Locations. 2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ,ESR 10 & ESR 11. |
No file Uploaded |
30-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM.
2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
30-04-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed |
No file Uploaded |
30-04-2021 |
1) Soil testing completed at all 7 CWRs Location.
2) Land not sufficient to accommodate structures at CWR 1, CWR2.
3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
30-04-2021 |
1) Soil testing completed at 12 Locations. 2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ,ESR 10 & ESR 11. |
No file Uploaded |
29-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM.
2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
29-04-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed |
No file Uploaded |
29-04-2021 |
1) Soil testing completed at all 7 CWRs Location.
2) Land not sufficient to accommodate structures at CWR 1, CWR2.
3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
29-04-2021 |
1) Soil testing completed at 12 Locations.
2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ,ESR 10 & ESR 11. |
No file Uploaded |
28-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
28-04-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed |
No file Uploaded |
28-04-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
28-04-2021 |
1) Soil testing completed at 12 Locations. 2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ,ESR 10 & ESR 11. |
No file Uploaded |
27-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
27-04-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed |
No file Uploaded |
27-04-2021 |
1) Soil testing completed at all 7 CWRs Location.
2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
27-04-2021 |
1) Soil testing completed at 12 Locations.
2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ,ESR 10 & ESR 11. |
No file Uploaded |
26-04-2021 |
1) Soil testing completed at all 7 CWRs Location.
2) Land not sufficient to accommodate structures at CWR 1, CWR2.
3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
26-04-2021 |
1) Soil testing completed at 12 Locations.
2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ,ESR 10 & ESR 11. |
No file Uploaded |
26-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM.
2. Laying of pipe line work commenced and completed as on date is 4.1 KM |
No file Uploaded |
26-04-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed |
No file Uploaded |
24-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM.
2. Laying of pipe line work commenced and completed as on date is 4.0 KM |
No file Uploaded |
24-04-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed |
No file Uploaded |
24-04-2021 |
1) Soil testing completed at all 7 CWRs Location.
2) Land not sufficient to accommodate structures at CWR 1, CWR2.
3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
24-04-2021 |
1) Soil testing completed at 12 Locations.
2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ,ESR 10 & ESR 11. |
No file Uploaded |
23-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM.
2. Laying of pipe line work commenced and completed as on date is 4.0 KM |
No file Uploaded |
23-04-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed |
No file Uploaded |
23-04-2021 |
1) Soil testing completed at all 7 CWRs Location.
2) Land not sufficient to accommodate structures at CWR 1, CWR2.
3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
23-04-2021 |
1) Soil testing completed in all location i.e. 11 Nos.
2) Rock Blasting Work in progress at CWR- 03 , CWR-04 , CWR-06, CWR-08, CWR 09 and CWR 10.
3) Land not sufficient to accommodate structures at CWR 01 and CWR 02 |
No file Uploaded |
23-04-2021 |
1) Soil testing completed at 12 Locations.
2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ,ESR 10 & ESR 11. |
No file Uploaded |
22-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM.
2. Laying of pipe line work commenced and completed as on date is 4.0 KM |
No file Uploaded |
22-04-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and sludge well Completed. 2) Excavation for Filter house Completed |
No file Uploaded |
22-04-2021 |
1) Soil testing completed at all 7 CWRs Location.
2) Land not sufficient to accommodate structures at CWR 1, CWR2.
3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
22-04-2021 |
1) Soil testing completed at 12 Locations.
2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ESR 10 & ESR 11. |
No file Uploaded |
21-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM.
2. Laying of pipe line work commenced and completed as on date is 4.0 KM |
No file Uploaded |
21-04-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and slude well Completed.
2) Excavation for Filter house Completed |
No file Uploaded |
21-04-2021 |
1) Soil testing completed at all 7 CWRs Location.
2) Land not sufficient to accommodate structures at CWR 1, CWR2.
3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
21-04-2021 |
1) Soil testing completed at 12 Locations.
2) Work in progress at ESR 01, ESR 04, ESR 06 ,ESR 08 ESR 10 & ESR 11. |
No file Uploaded |
20-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.0 KM |
No file Uploaded |
20-04-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and slude well Completed. 2) Rock blasting and excavation in progress for Filter house |
No file Uploaded |
20-04-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
20-04-2021 |
1) Soil testing completed at 12 Locations. 2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11. |
No file Uploaded |
19-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.2 KM |
No file Uploaded |
19-04-2021 |
1) PCC for Cascade Aerator, Flash mixer , Filter House , Chmical House , Sludge well and Chlorine Building Completed. 2) Rock Blasting and Excavation in progress at both Clariflocculators |
No file Uploaded |
19-04-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
19-04-2021 |
1) Soil testing completed at 12 Locations.
2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11. |
No file Uploaded |
18-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.2 KM |
No file Uploaded |
18-04-2021 |
1) PCC for Cascade Aerator, Flash mixer , Filter House , Chmical House , Sludge well and Chlorine Building Completed. 2) Rock Blasting and Excavation in progress at both Clariflocculators |
No file Uploaded |
18-04-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
18-04-2021 |
1) Soil testing completed at 12 Locations. 2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11. |
No file Uploaded |
17-04-2021 |
1) PCC for Cascade Aerator, Flash mixer , Clariflocculator outer wall , Chemical House and Chlorine Building and slude well Completed.
2) Rock blasting and excavation in progress for Filter house |
No file Uploaded |
17-04-2021 |
1) Soil testing completed at all 7 CWRs Location.
2) Land not sufficient to accommodate structures at CWR 1, CWR2.
3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
17-04-2021 |
1) Soil testing completed at 12 Locations. 2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11. |
No file Uploaded |
16-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.2 KM |
No file Uploaded |
16-04-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress for several structures i.e. Pipeline from Flash mixer to CLF, Sludge well pipeline, Filter beds etc... PCC work for Cascade Aerator, Raw water channel, Chemical House, chlorine house, Flash Mixers and Sludge well completed. |
No file Uploaded |
16-04-2021 |
1) Soil testing completed at all 7 CWRs Location. 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
16-04-2021 |
1) Soil testing completed at 12 Locations. 2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11. |
No file Uploaded |
15-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.2 KM |
No file Uploaded |
15-04-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress for several structures i.e. Pipeline from Flash mixer to CLF, Sludge well pipeline, Filter beds etc...
PCC work for Cascade Aerator, Raw water channel, Chemical House, chlorine house, Flash Mixers and Sludge well completed. |
No file Uploaded |
15-04-2021 |
1) Soil testing completed at all 7 CWRs Location.
2) Land not sufficient to accommodate structures at CWR 1, CWR2.
3) Work in progress at CWR 3 and CWR 5. |
No file Uploaded |
15-04-2021 |
1) Soil testing completed at 12 Locations.
2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11. |
No file Uploaded |
14-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.2 KM |
No file Uploaded |
14-04-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC work for Cascade Aerator, Raw water channel, Chemical House, chlorine house, Flash Mixers and Sludge well completed. |
No file Uploaded |
14-04-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
14-04-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11. |
No file Uploaded |
13-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.2 KM |
No file Uploaded |
13-04-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC work for Cascade Aerator, Chemical House and chlorine house, Flash Mixers and Sludge well completed |
No file Uploaded |
13-04-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
13-04-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11. |
No file Uploaded |
12-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.2 KM |
No file Uploaded |
12-04-2021 |
1) Soil testing completed in all location i.e., 11 Nos 2) Work in progress at CWR- 03 , CWR-04 , CWR-06, CWR-08, CWR 09 and CWR 10 3) Land not sufficient to accommodate structures at CWR 01 and CWR 02 |
No file Uploaded |
12-04-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
12-04-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11. |
No file Uploaded |
10-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.2 KM |
No file Uploaded |
10-04-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC work for Cascade Aerator, Chemical House and chlorine house completed. |
No file Uploaded |
10-04-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
10-04-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11. |
No file Uploaded |
09-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.2 KM |
No file Uploaded |
09-04-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC work for Cascade Aerator, Chemical House and chlorine house completed. |
No file Uploaded |
09-04-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
09-04-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11. |
No file Uploaded |
08-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.2 KM |
No file Uploaded |
08-04-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC work for Cascade Aerator, Chemical House and chlorine house completed. |
No file Uploaded |
08-04-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
08-04-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11. |
No file Uploaded |
07-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.2 KM |
No file Uploaded |
07-04-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC work for Cascade Aerator, Chemical House and chlorine house completed. |
No file Uploaded |
07-04-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
07-04-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11. |
No file Uploaded |
06-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM.
2. Laying of pipe line work commenced and completed as on date is 4.2 KM |
No file Uploaded |
06-04-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC work for Raw water channel, Chemical House and chlorine house completed. |
No file Uploaded |
06-04-2021 |
1) Soil testing completed at all 7 CWRs Location
2) Land not sufficient to accommodate structures at CWR 1, CWR2
3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
06-04-2021 |
1) Soil testing completed at 12 Locations
2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11. |
No file Uploaded |
05-04-2021 |
1.DI Pipes 700 mm Dia. Received at Site 5.0 KM.
2. Laying of pipe line work commenced and completed as on date is 4.2 KM |
No file Uploaded |
05-04-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC work for Raw water channel, Chemical House and chlorine house completed. |
No file Uploaded |
05-04-2021 |
1) Soil testing completed at all 7 CWRs Location
2) Land not sufficient to accommodate structures at CWR 1, CWR2
3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
05-04-2021 |
1) Soil testing completed at 12 Locations
2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11. |
No file Uploaded |
04-04-2021 |
DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.0 KM |
No file Uploaded |
04-04-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
04-04-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11. |
No file Uploaded |
03-04-2021 |
DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.0 KM WORK STOPPED BY KISAAN UNIONS FROM 09.03.2021 |
No file Uploaded |
03-04-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
03-04-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11 |
No file Uploaded |
02-04-2021 |
DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.0 KM WORK STOPPED BY KISAAN UNIONS FROM 09.03.2021 |
No file Uploaded |
02-04-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC work for Raw water channel, Chemical House and chlorine house completed. |
No file Uploaded |
02-04-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
02-04-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11 |
No file Uploaded |
01-04-2021 |
DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.0 KM WORK STOPPED BY KISAAN UNIONS FROM 09.03.2021 |
No file Uploaded |
01-04-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC work for Raw water channel, Chemical House and chlorine house completed. |
No file Uploaded |
01-04-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
01-04-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11 |
No file Uploaded |
27-03-2021 |
DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.0 KM WORK STOPPED BY KISAAN UNIONS FROM 09.03.2021 |
No file Uploaded |
27-03-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC work for Chemical House and chlorine house completed. |
No file Uploaded |
27-03-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
27-03-2021 |
1) Soil testing completed at 12 Locations
2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11 |
No file Uploaded |
26-03-2021 |
DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.0 KM WORK STOPPED BY KISAN UNIONS FROM 09.03.2021 |
No file Uploaded |
26-03-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC work for Chemical House and chlorine house completed. |
No file Uploaded |
26-03-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
26-03-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
26-03-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 02, ESR 04- ESR -10, ESR 11 & ESR-12 |
No file Uploaded |
26-03-2021 |
DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.0 KM WORK STOPPED BY KISAAN UNIONS FROM 09.03.2021 |
No file Uploaded |
26-03-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC work for Chemical House and chlorine house completed. |
No file Uploaded |
26-03-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
26-03-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 04, ESR 06 ESR 10 & ESR 11 |
No file Uploaded |
25-03-2021 |
DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.0 KM WORK STOPPED BY KISAN UNIONS FROM 09.03.2021 |
No file Uploaded |
25-03-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC work for Chemical House and chlorine house completed. |
No file Uploaded |
25-03-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2
3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
25-03-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 02, ESR 04- ESR -10, ESR 11 & ESR-12 |
No file Uploaded |
24-03-2021 |
DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.0 KM WORK STOPPED BY KISAN UNIONS FROM 09.03.2021 |
No file Uploaded |
24-03-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC work for Chemical House and chlorine house completed. |
No file Uploaded |
24-03-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
24-03-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 02, ESR 04- ESR -10, ESR 11 & ESR-12 |
No file Uploaded |
23-03-2021 |
DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Laying of pipe line work commenced and completed as on date is 4.0 KM WORK STOPPED BY KISAN UNIONS FROM 09.03.2021 |
No file Uploaded |
23-03-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC work for Chemical House and chlorine house completed. |
No file Uploaded |
23-03-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
23-03-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 02, ESR 04- ESR -10, ESR 11 & ESR-12 |
No file Uploaded |
22-03-2021 |
DI Pipes 700 mm Dia. Received at Site 5.0 KM.
2. Laying of pipe line work commenced and completed as on date is 4.4 KM WORK STOPPED BY KISAN UNIONS FROM 09.03.2021 |
No file Uploaded |
22-03-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC work for Chemical House and chlorine house completed. |
No file Uploaded |
22-03-2021 |
1) Soil testing completed at all 7 CWRs Location
2) Land not sufficient to accommodate structures at CWR 1, CWR2
3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
22-03-2021 |
1) Soil testing completed at 12 Locations
2) Work in progress at ESR 01, ESR 02, ESR 04- ESR -10, ESR 11 & ESR-12 |
No file Uploaded |
19-03-2021 |
DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Execution Team with Machinery Mobilized on Site. 3. Laying of pipe line work commenced and completed as on date is 4.4 KM WORK STOPPED BY KISAN UNIONS FROM 09.03.2021 |
No file Uploaded |
19-03-2021 |
Soil testing completed. Rock Blasting and Excavation work in progress. PCC for chemical house and Chlorine house footings completed |
No file Uploaded |
19-03-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
19-03-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 02, ESR 04- ESR -10, ESR 11 & ESR-12 |
No file Uploaded |
18-03-2021 |
DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Execution Team with Machinery Mobilized on Site. 3. Laying of pipe line work commenced and completed as on date is 4.4 KM WORK STOPPED BY KISAN UNIONS FROM 09.03.202 |
No file Uploaded |
18-03-2021 |
Soil testing completed. Rock Blasting and Excavation work in progress. PCC for chemical house and Chlorine house footings completed |
No file Uploaded |
18-03-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
18-03-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 02, ESR 04- ESR -10, ESR 11 & ESR-12 |
No file Uploaded |
17-03-2021 |
DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Execution Team with Machinery Mobilized on Site. 3. Laying of pipe line work commenced and completed as on date is 4.4 KM WORK STOPPED BY KISAN UNIONS FROM 09.03.202 |
No file Uploaded |
17-03-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC work for Chemical House and Chlorine House is in progress. |
No file Uploaded |
17-03-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
17-03-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 02, ESR 04- ESR -10, ESR 11 & ESR-12 |
No file Uploaded |
16-03-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC for chemical house and Chlorine house is in progress. |
No file Uploaded |
16-03-2021 |
1) Soil testing completed at all 7 CWRs Location
2) Land not sufficient to accommodate structures at CWR 1, CWR2 and CWR 6
3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
16-03-2021 |
1) Soil testing completed at all 7 CWRs Location
2) Land not sufficient to accommodate structures at CWR 1, CWR2 and CWR 6
3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
16-03-2021 |
1) Soil testing completed at 12 Locations
2) Work in progress at ESR 01, ESR 02, ESR 04- ESR -10, ESR 11 & ESR-12 |
No file Uploaded |
16-03-2021 |
DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Execution Team with Machinery Mobilized on Site. 3. Laying of pipe line work commenced and completed as on date is 4.4 KM WORK STOPPED BY KISAN UNIONS FROM 09.03.202 |
No file Uploaded |
15-03-2021 |
DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Execution Team with Machinery Mobilized on Site. 3. Laying of pipe line work commenced and completed as on date is 4.05 KM WORK STOPPED BY KISAN UNIONS FROM 09.03.2021 |
No file Uploaded |
15-03-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2 and CWR 6 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
15-03-2021 |
1) Soil testing completed at 12 Locations 2) Work in progress at ESR 01, ESR 4- ESR -06, ESR 09 & ESR-10 |
No file Uploaded |
15-03-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. PCC for chemical house completed. PCC work for Chlorine house is in progress. |
No file Uploaded |
13-03-2021 |
Soil testing completed. Hard rock encountered at all structures - Blasting and Excavation work in progress. |
No file Uploaded |
13-03-2021 |
DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Execution Team with Machinery Mobilized on Site. 3. Laying of pipe line work commenced and completed as on date is 4.05 KM
WORK STOPPED BY KISAN UNIONS FROM 09.03.2021 |
No file Uploaded |
13-03-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
12-03-2021 |
DI Pipes 700 mm Dia. Received at Site 5.0 KM. 2. Execution Team with Machinery Mobilized on Site. 3. Laying of pipe line work commenced and completed as on date is 4.05 KM |
No file Uploaded |
12-03-2021 |
1) Soil testing completed at all 7 CWRs Location 2) Land not sufficient to accommodate structures at CWR 1, CWR2. 3) Work in progress at CWR 3 and CWR 5 |
No file Uploaded |
45 |
Dhauha GOV Water Supply Scheme |
Megha Engineering |
11-05-2022 |
Comment Intake well: Motor slab completed Pump house columns work in progress- Approach bridge deck slab completed Switch yard 80% completed - Source to Intake well pipe line 80 % completed |
No file Uploaded |
11-05-2022 |
Comment DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 4.1 KM |
No file Uploaded |
11-05-2022 |
Comment 1) Aerator- 100 % Completed 2 ) Raw water Channel ,Flash mixers - 100 % completed 3) Chemical House & Chlorine house finishing work in progress 4) Clari flocculator 95 % completed- 5) Filter beds top slab completed 6) wash water tank - 85% completed |
No file Uploaded |
11-05-2022 |
1) Work in progress at CWR-01,CWR - 02, CWR 3 , CWR 04, CWR 5,CWR 6, CWR 07,CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
11-05-2022 |
Except ESR - 17 all other ESR (24nos) Work in progress. |
No file Uploaded |
11-05-2022 |
Clear water pipe line : Excavation and laying completed - 106 KM |
No file Uploaded |
11-05-2022 |
Distribution System : Excavation, Laying Completed 387 KM |
No file Uploaded |
11-05-2022 |
FHTC Completed 2126 Nos. |
No file Uploaded |
11-05-2022 |
1.DI Pipes 700 mm Dia. Received at Site 15 KM. 2. Laying of pipe line work commenced and completed as on date 14.8 KM- Hydro testing completed 8 KM |
No file Uploaded |
11-05-2022 |
Aerator- 95 % Completed 2 ) Raw water Channel ,Flash mixers - 95 % completed 3) Chemical House & Chlorine house finishing work in progress 4) Clari flocculator 95 % completed- 5) Filter beds top slab completed 6) wash water tank - 85% completed |
No file Uploaded |
04-05-2022 |
Comment Intake well: Motor slab completed Pump house columns work in progress- Approach bridge deck slab completed Switch yard 80% completed - Source to Intake well pipe line 80 % completed |
No file Uploaded |
04-05-2022 |
Comment DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 3.9 KM |
No file Uploaded |
04-05-2022 |
Comment 1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house finishing work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab completed 6) wash water tank - 80% completed |
No file Uploaded |
04-05-2022 |
1) Work in progress at CWR-01,CWR - 02, CWR 3 , CWR 04, CWR 5,CWR 6, CWR 07,CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
04-05-2022 |
Except ESR - 17 all other ESR (24nos) Work in progress. |
No file Uploaded |
04-05-2022 |
Clear water pipe line : Excavation and laying completed - 103 KM |
No file Uploaded |
04-05-2022 |
Distribution System : Excavation, Laying Completed 364 KM |
No file Uploaded |
04-05-2022 |
FHTC Completed 1640 Nos. |
No file Uploaded |
27-04-2022 |
Comment Intake well: Motor slab completed Pump house columns work in progress- Approach bridge deck slab completed Switch yard 80% completed - Source to Intake well pipe line 80 % completed |
No file Uploaded |
27-04-2022 |
Comment DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 3.7 KM |
No file Uploaded |
27-04-2022 |
Comment 1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house finishing work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab completed 6) wash water tank - 80% completed |
No file Uploaded |
27-04-2022 |
1) Work in progress at CWR-01,CWR - 02, CWR 3 , CWR 04, CWR 5,CWR 6, CWR 07,CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
27-04-2022 |
Except ESR - 17 all other ESR (24nos) Work in progress. |
No file Uploaded |
27-04-2022 |
Clear water pipe line : Excavation and laying completed - 97 KM |
No file Uploaded |
27-04-2022 |
Distribution System : Excavation, Laying Completed 348 KM |
No file Uploaded |
27-04-2022 |
FHTC Completed 1210 Nos. |
No file Uploaded |
20-04-2022 |
Comment Intake well: Motor slab completed Pump house columns work in progress- Approach bridge deck slab completed Switch yard 80% completed - Source to Intake well pipe line 80 % completed |
No file Uploaded |
20-04-2022 |
Comment DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 3.7 KM |
No file Uploaded |
20-04-2022 |
Comment 1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house finishing work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab completed 6) wash water tank - 80% completed |
No file Uploaded |
20-04-2022 |
1) Work in progress at CWR-01,CWR - 02, CWR 3 , CWR 04, CWR 5,CWR 6, CWR 07,CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
20-04-2022 |
Except ESR - 17 all other ESR (24nos) Work in progress. |
No file Uploaded |
20-04-2022 |
Clear water pipe line : Excavation and laying completed - 95 KM |
No file Uploaded |
20-04-2022 |
Distribution System : Excavation, Laying Completed 336 KM |
No file Uploaded |
20-04-2022 |
FHTC Completed 980 Nos. |
No file Uploaded |
13-04-2022 |
Comment Intake well: Motor slab completed Pump house columns work in progress- Approach bridge deck slab completed Switch yard 80% completed - Source to Intake well pipe line 80 % completed |
No file Uploaded |
13-04-2022 |
Comment DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 3.7 KM |
No file Uploaded |
13-04-2022 |
Comment 1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house finishing work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab completed 6) wash water tank - 80% completed |
No file Uploaded |
13-04-2022 |
1) Work in progress at CWR-01,CWR - 02, CWR 3 , CWR 04, CWR 5,CWR 6, CWR 07,CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
13-04-2022 |
Except ESR - 17 all other ESR (24nos) Work in progress. |
No file Uploaded |
13-04-2022 |
Clear water pipe line : Excavation and laying completed - 93 KM |
No file Uploaded |
13-04-2022 |
Distribution System : Excavation, Laying Completed 324 KM |
No file Uploaded |
13-04-2022 |
FHTC Completed 460 Nos. |
No file Uploaded |
06-04-2022 |
Intake well: Motor slab completed Pump house columns work in progress- Approach bridge deck slab in progress Switch yard 80% completed - Source to Intake well pipe line 80 % completed |
No file Uploaded |
06-04-2022 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 3.5 KM |
No file Uploaded |
06-04-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house finishing work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab completed 6) wash water tank - 80% completed |
No file Uploaded |
06-04-2022 |
1) Work in progress at CWR-01,CWR - 02, CWR 3 , CWR 04, CWR 5,CWR 6, CWR 07,CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
06-04-2022 |
Except ESR - 17 all other ESR (24nos) Work in progress. |
No file Uploaded |
06-04-2022 |
Clear water pipe line : Excavation and laying completed - 86 KM |
No file Uploaded |
06-04-2022 |
Distribution System : Excavation, Laying Completed 313 KM |
No file Uploaded |
06-04-2022 |
FHTC Completed 410 Nos. |
No file Uploaded |
02-04-2022 |
Intake well: Motor slab completed Pump house columns work in progress- Approach bridge deck slab in progress Switch yard 80% completed - Source to Intake well pipe line 80 % completed |
No file Uploaded |
02-04-2022 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 3.5 KM |
No file Uploaded |
02-04-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house finishing work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab completed 6) wash water tank - 80% completed |
No file Uploaded |
02-04-2022 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 07,CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
02-04-2022 |
Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 16,ESR 20, ESR 21, ESR 22, ESR 24 & ESR 25 |
No file Uploaded |
02-04-2022 |
Distribution System : Excavation, Laying Completed 301 KM |
No file Uploaded |
02-04-2022 |
Clear water pipe line : Excavation and laying completed - 86 KM |
No file Uploaded |
02-04-2022 |
Clear water pipe line : Excavation and laying completed - 40 KM |
No file Uploaded |
30-03-2022 |
Intake well: Motor slab completed - Switch yard - Column completed up to 6 m ht . pipe line completed 70 Mtrs out of 100 Mtrs |
No file Uploaded |
30-03-2022 |
1) Work in progress at CWR-01, CWR 2 CWR 03, CWR 04 ,CWR 6 & CWR -07 |
No file Uploaded |
30-03-2022 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 3.5 KM |
No file Uploaded |
30-03-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house finishing work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab completed 6) wash water tank - 80% completed |
No file Uploaded |
30-03-2022 |
Clear water pipe line : Excavation and laying completed - 86 KM |
No file Uploaded |
30-03-2022 |
Distribution System : Excavation, Laying Completed 301 KM |
No file Uploaded |
30-03-2022 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 07,CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
30-03-2022 |
Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 16,ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
23-03-2022 |
Intake well: Motor slab completed - Switch yard - Column completed up to 6 m ht . pipe line completed 70 Mtrs out of 100 Mtrs |
No file Uploaded |
23-03-2022 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 3.5 KM |
No file Uploaded |
23-03-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house finishing work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab completed 6) wash water tank - 90% completed |
No file Uploaded |
23-03-2022 |
Clear water pipe line : Excavation and laying completed - 84 KM |
No file Uploaded |
23-03-2022 |
Distribution System : Excavation, Laying Completed 288 KM |
No file Uploaded |
23-03-2022 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 07,CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
23-03-2022 |
Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 16,ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
09-03-2022 |
Intake well: Motor slab in progress - Switch yard - Column completed up to 6 m ht . pipe line completed 70 Mtrs out of 100 Mtrs |
No file Uploaded |
09-03-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Plastering work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab work in progress 6) wash water tank - 80% completed |
No file Uploaded |
09-03-2022 |
Clear water pipe line : Excavation and laying completed - 84 KM |
No file Uploaded |
09-03-2022 |
Distribution System : Excavation, Laying Completed 278 KM |
No file Uploaded |
09-03-2022 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 07,CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
09-03-2022 |
Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 16,ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
02-03-2022 |
Intake well: Motor base slab shuttering work in progress - Switch yard - Columns up to 1 st brace beam completed |
No file Uploaded |
02-03-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Plastering work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab work in progress 6) wash water tank - 80% completed |
No file Uploaded |
02-03-2022 |
Clear water pipe line : Excavation and laying completed - 84 KM |
No file Uploaded |
02-03-2022 |
Distribution System : Excavation, Laying Completed 267 KM |
No file Uploaded |
02-03-2022 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 07,CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
02-03-2022 |
Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 16,ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
23-02-2022 |
Intake well: Motor base slab shuttering work in progress - Switch yard - Columns up to 1 st brace beam completed |
No file Uploaded |
23-02-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Plastering work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab work in progress 6) wash water tank - 80% completed |
No file Uploaded |
23-02-2022 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 3.5 KM |
No file Uploaded |
23-02-2022 |
Clear water pipe line : Excavation and laying completed - 84 KM |
No file Uploaded |
23-02-2022 |
Distribution System : Excavation, Laying Completed 236 KM |
No file Uploaded |
23-02-2022 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
23-02-2022 |
Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
14-02-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Plastering work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab work in progress 6) wash water tank - 80% completed
|
No file Uploaded |
14-02-2022 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR -09, CWR10 & CWR 11
|
No file Uploaded |
14-02-2022 |
Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24
|
No file Uploaded |
12-02-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Plastering work in progress 4) Clari flocculator 90 % completed- 5) Filter beds top slab work in progress 6) wash water tank - 80% completed
|
No file Uploaded |
12-02-2022 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR -09, CWR10 & CWR 11
|
No file Uploaded |
12-02-2022 |
Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24
|
No file Uploaded |
09-02-2022 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 3.5 KM |
No file Uploaded |
09-02-2022 |
Intake well: Side wall completed up to Motor base slab - Switch yard - Columns up to 1 st brace beam completed |
No file Uploaded |
09-02-2022 |
1) Aerator- , Raw water Channel ,Flash mixers , Chemical House & Chlorine house completed 2) Clari flocculator 90 % completed 3) Filter House 80 % completed 4) Wash water tank 80 % completed |
No file Uploaded |
09-02-2022 |
Clear water pipe line : Excavation and laying completed - 84 KM |
No file Uploaded |
09-02-2022 |
Distribution System : Completed 195 KM in Zone 02 , Zone 04 & Zone 05 ,Zone 15 & Zone 13 |
No file Uploaded |
09-02-2022 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
09-02-2022 |
Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
02-02-2022 |
Intake well: Side wall completed up to Motor base slab - Switch yard - Columns up to 1 st brace beam completed |
No file Uploaded |
02-02-2022 |
1) Aerator- , Raw water Channel ,Flash mixers , Chemical House & Chlorine house completed 2) Clari flocculator 90 % completed 3) Filter House 80 % completed 4) Wash water tank 80 % completed |
No file Uploaded |
02-02-2022 |
Clear water pipe line : Excavation and laying completed - 84 KM |
No file Uploaded |
02-02-2022 |
Distribution System : Completed 195 KM in Zone 02 , Zone 04 & Zone 05 ,Zone 15 & Zone 13 |
No file Uploaded |
02-02-2022 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
02-02-2022 |
Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
25-01-2022 |
Intake well: 16 th lift in progress - Switch yard - Columns up to 1 st brace beam completed |
No file Uploaded |
25-01-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Plastering work in progress 4) Clari flocculator 70 % completed- 5) Filter beds up to walkway completed |
No file Uploaded |
25-01-2022 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 3.5 KM |
No file Uploaded |
25-01-2022 |
Clear water pipe line : Excavation and laying completed - 84 KM |
No file Uploaded |
25-01-2022 |
Distribution System : Completed 187KM in Zone 02 , Zone 04 & Zone 05 ,Zone 15 & Zone 13 |
No file Uploaded |
25-01-2022 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
25-01-2022 |
Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
19-01-2022 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 3.5 KM |
No file Uploaded |
19-01-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Plastering work in progress 4) Clari flocculator Outer Launder in progress - 5) Filter beds up to walkway completed 6) Wash water tank side wall in progress |
No file Uploaded |
19-01-2022 |
Clear water pipe line : Excavation and laying completed - 84 KM |
No file Uploaded |
19-01-2022 |
Distribution System : Completed 192KM in Zone 02 , Zone 04 & Zone 05 ,Zone 15 & Zone 13 |
No file Uploaded |
19-01-2022 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
19-01-2022 |
Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
12-01-2022 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 3.5 KM |
No file Uploaded |
12-01-2022 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Plastering work in progress 4) Clari flocculator Outer Launder in progress - 5) Filter beds up to walkway completed 6) Wash water tank bottom slab completed |
No file Uploaded |
12-01-2022 |
Clear water pipe line : Excavation and laying completed - 84 KM |
No file Uploaded |
12-01-2022 |
Distribution System : Completed 187 KM in Zone 02 , Zone 04 & Zone 05 ,Zone 15 & Zone 13 |
No file Uploaded |
12-01-2022 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
12-01-2022 |
Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
29-12-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 3.2 KM |
No file Uploaded |
29-12-2021 |
1) Aerator- 90 % Completed 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Plastering work in progress 4) Clari flocculator Outer Launder in progress - 5) Filter beds up to walkway completed 6) Wash water tank bottom slab completed |
No file Uploaded |
29-12-2021 |
Clear water pipe line : Excavation and laying completed - 84 KM |
No file Uploaded |
29-12-2021 |
Distribution System : Completed 169 KM in Zone 02 , Zone 04 & Zone 05 ,Zone 15 & Zone 13 |
No file Uploaded |
29-12-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
29-12-2021 |
Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
22-12-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 3.2 KM |
No file Uploaded |
22-12-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 3 beds PCC completed out of 6 Nos |
No file Uploaded |
22-12-2021 |
Clear water pipe line : Excavation and laying completed - 84 KM |
No file Uploaded |
22-12-2021 |
Distribution System : Completed 165 KM in Zone 02 , Zone 04 & Zone 05 ,Zone 15 & Zone 13 |
No file Uploaded |
22-12-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
22-12-2021 |
Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
15-12-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 3,2 KM |
No file Uploaded |
15-12-2021 |
1) Aerator- Completed 90 % 2 ) Raw water Channel ,Flash mixers - 90 % completed 3) Chemical House & Chlorine house Brick work in progress 4) Clari flocculator Outer wall concrete 70% completed - 5) Filter beds up to walkway completed |
No file Uploaded |
15-12-2021 |
Clear water pipe line : Excavation and laying completed - 84 KM |
No file Uploaded |
15-12-2021 |
Distribution System : Completed 152 KM in Zone 02 , Zone 04 & Zone 05 ,Zone 15 & Zone 13 |
No file Uploaded |
15-12-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
15-12-2021 |
Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
08-12-2021 |
1) Aerator- Completed 90 % 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house Brick work in progress 4) Clari flocculator Outer wall concrete 70% completed - 5) Filter beds up to walkway completed |
No file Uploaded |
08-12-2021 |
Clear water pipe line : Excavation and laying completed - 80 KM |
No file Uploaded |
08-12-2021 |
Distribution System : Completed 145 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
08-12-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
08-12-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
01-12-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 3 KM |
No file Uploaded |
01-12-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house roof completed 4) Clari flocculator Outer wall concrete completed - 5) Filter beds Bottom side walls completed |
No file Uploaded |
01-12-2021 |
Clear water pipe line : Excavation and laying completed - 76 KM |
No file Uploaded |
01-12-2021 |
Distribution System : Completed 138 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
01-12-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR -09, CWR10 & CWR 11 |
No file Uploaded |
01-12-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
11-11-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
11-11-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 be |
No file Uploaded |
11-11-2021 |
Clear water pipe line : Excavation and laying completed - 28 KM |
No file Uploaded |
11-11-2021 |
Distribution System : Completed 70 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
11-11-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
11-11-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
10-11-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
10-11-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft comple |
No file Uploaded |
10-11-2021 |
Clear water pipe line : Excavation and laying completed - 27 KM |
No file Uploaded |
10-11-2021 |
Distribution System : Completed 60 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
10-11-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
10-11-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
08-11-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
08-11-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft comple |
No file Uploaded |
08-11-2021 |
Clear water pipe line : Excavation and laying completed - 27 KM |
No file Uploaded |
08-11-2021 |
Distribution System : Completed 60 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
08-11-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
08-11-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
27-10-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
27-10-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft comple |
No file Uploaded |
27-10-2021 |
Clear water pipe line : Excavation and laying completed - 27 KM |
No file Uploaded |
27-10-2021 |
Distribution System : Completed 57 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
27-10-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
27-10-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
26-10-2021 |
Distribution System : Completed 55 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
26-10-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
26-10-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
26-10-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
26-10-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft comple |
No file Uploaded |
26-10-2021 |
Clear water pipe line : Excavation and laying completed - 27 KM |
No file Uploaded |
20-10-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
20-10-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft comple |
No file Uploaded |
20-10-2021 |
Clear water pipe line : Excavation and laying completed - 23 KM |
No file Uploaded |
20-10-2021 |
Distribution System : Completed 50 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
20-10-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
20-10-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
19-10-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
19-10-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft comple |
No file Uploaded |
19-10-2021 |
Clear water pipe line : Excavation and laying completed - 23 KM |
No file Uploaded |
19-10-2021 |
Distribution System : Completed 49 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
19-10-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
19-10-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
18-10-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
18-10-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft comple |
No file Uploaded |
18-10-2021 |
Clear water pipe line : Excavation and laying completed - 23 KM |
No file Uploaded |
18-10-2021 |
Distribution System : Completed 45 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
18-10-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
18-10-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
16-10-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
16-10-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft comple |
No file Uploaded |
16-10-2021 |
Clear water pipe line : Excavation and laying completed - 23 KM |
No file Uploaded |
16-10-2021 |
Distribution System : Completed 44 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
16-10-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
16-10-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
13-10-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
13-10-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft comple |
No file Uploaded |
13-10-2021 |
Clear water pipe line : Excavation and laying completed - 22 KM |
No file Uploaded |
13-10-2021 |
Distribution System : Completed 42 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
13-10-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
13-10-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
12-10-2021 |
Intake well: 1 st concrete completed - Switch yard - Footings completed - Column reinforcement in progress completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
12-10-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
12-10-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft completed out of 6 Nos |
No file Uploaded |
12-10-2021 |
Clear water pipe line : Excavation and laying completed - 22 KM |
No file Uploaded |
12-10-2021 |
Distribution System : Completed 40 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
12-10-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
12-10-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
11-10-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
11-10-2021 |
Clear water pipe line : Excavation and laying completed - 19.7 KM |
No file Uploaded |
11-10-2021 |
Distribution System : Completed 40 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
11-10-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
11-10-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
06-10-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
06-10-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft completed out of 6 Nos |
No file Uploaded |
06-10-2021 |
Clear water pipe line : Excavation and laying completed - 18 KM |
No file Uploaded |
06-10-2021 |
Distribution System : Completed 37 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
06-10-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
06-10-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
05-10-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
05-10-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
05-10-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft completed out of 6 Nos |
No file Uploaded |
05-10-2021 |
Clear water pipe line : Excavation and laying completed - 17.5 KM |
No file Uploaded |
05-10-2021 |
Distribution System : Completed 37 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
05-10-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
05-10-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
04-10-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
04-10-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft completed out of 6 Nos |
No file Uploaded |
04-10-2021 |
Clear water pipe line : Excavation and laying completed - 17 KM |
No file Uploaded |
04-10-2021 |
Distribution System : Completed 36 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
04-10-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
04-10-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
29-09-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
29-09-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft completed out of 6 Nos |
No file Uploaded |
29-09-2021 |
Clear water pipe line : Excavation and laying completed - 14.5 KM |
No file Uploaded |
29-09-2021 |
Distribution System : Completed 29 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
29-09-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
29-09-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
28-09-2021 |
Intake well: Raft completed- Switch yard - Foundation PCC completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
28-09-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
28-09-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft completed out of 6 Nos |
No file Uploaded |
28-09-2021 |
Clear water pipe line : Excavation and laying completed - 14 KM |
No file Uploaded |
28-09-2021 |
Distribution System : Completed 25 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
28-09-2021 |
Staff quarters : Work in progress at CWR +PH -03 |
No file Uploaded |
28-09-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft completed out of 6 Nos |
No file Uploaded |
28-09-2021 |
) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
27-09-2021 |
Intake well: Raft completed- Switch yard - Foundation PCC completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
27-09-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
27-09-2021 |
Clear water pipe line : Excavation and laying completed - 14 KM |
No file Uploaded |
27-09-2021 |
Distribution System : Completed 25 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
27-09-2021 |
1) Aerator- Up to bottom slab completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to roof level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 5 beds Raft completed out of 6 Nos |
No file Uploaded |
27-09-2021 |
Staff quarters : Work in progress at CWR +PH -03 |
No file Uploaded |
27-09-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
27-09-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
22-09-2021 |
Intake well: PCC Completed. Raft reinforcement work completed- Switch yard - Foundation PCC completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
22-09-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department and Railway permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
22-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 3 beds PCC completed out of 6 Nos |
No file Uploaded |
22-09-2021 |
Clear water pipe line : Excavation and laying completed - 12.5 KM |
No file Uploaded |
22-09-2021 |
Distribution System : Completed 22 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
22-09-2021 |
Staff quarters : Work in progress at CWR +PH -03 |
No file Uploaded |
22-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 3 beds PCC completed out of 6 Nos |
No file Uploaded |
22-09-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
22-09-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
21-09-2021 |
Intake well: PCC Completed. Raft reinforcement work completed- Switch yard - Foundation PCC completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
21-09-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department and Railway permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
21-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 3 beds PCC completed out of 6 Nos |
No file Uploaded |
21-09-2021 |
Clear water pipe line : Excavation and laying completed - 11.7 KM |
No file Uploaded |
21-09-2021 |
Distribution System : Completed 21 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
21-09-2021 |
Staff quarters : Work in progress at CWR +PH -03 |
No file Uploaded |
21-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 3 beds PCC completed out of 6 Nos |
No file Uploaded |
21-09-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
21-09-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
21-09-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
20-09-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department and Railway permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
20-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 3 beds PCC completed out of 6 Nos |
No file Uploaded |
20-09-2021 |
Clear water pipe line : Excavation and laying completed - 11.5 KM |
No file Uploaded |
20-09-2021 |
Distribution System : Completed 20 KM in Zone 04 , Zone 15 & Zone 13 , Zone -02 |
No file Uploaded |
20-09-2021 |
Staff quarters : Work in progress at CWR +PH -03 |
No file Uploaded |
20-09-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
20-09-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
15-09-2021 |
Intake well: PCC Completed. Raft reinforcement work completed- Switch yard - Foundation PCC completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
15-09-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department and Railway permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
15-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 3 beds PCC completed out of 6 Nos |
No file Uploaded |
15-09-2021 |
Clear water pipe line : Excavation and laying completed - 11 KM |
No file Uploaded |
15-09-2021 |
Distribution System : Completed 17 KM in Zone 04 , Zone 15 |
No file Uploaded |
15-09-2021 |
Staff quarters : Work in progress at CWR +PH -03 |
No file Uploaded |
15-09-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
15-09-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
14-09-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
14-09-2021 |
Clear water pipe line : Excavation and laying completed - 11 KM |
No file Uploaded |
14-09-2021 |
Distribution System : Completed 16.5 KM in Zone 4 & Zone 15 |
No file Uploaded |
14-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 3 beds PCC completed out of 6 Nos |
No file Uploaded |
14-09-2021 |
Staff quarters : Work in progress at CWR +PH -03 |
No file Uploaded |
14-09-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
14-09-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
13-09-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
13-09-2021 |
Clear water pipe line : Excavation and laying completed - 11 KM |
No file Uploaded |
13-09-2021 |
Distribution System : Completed 15.6 KM in Zone 4 & Zone 15 |
No file Uploaded |
13-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 3 beds PCC completed out of 6 Nos |
No file Uploaded |
13-09-2021 |
Staff quarters : Work in progress at CWR +PH -03 |
No file Uploaded |
13-09-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
13-09-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
12-09-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
12-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 3 beds PCC completed out of 6 Nos |
No file Uploaded |
12-09-2021 |
Staff quarters : Work in progress at CWR +PH -03 |
No file Uploaded |
12-09-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
12-09-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
12-09-2021 |
Distribution System : Completed 17 KM in Zone 4 & Zone 15 |
No file Uploaded |
12-09-2021 |
Clear water pipe line : Excavation and laying completed - 11 KM |
No file Uploaded |
08-09-2021 |
Intake well: PCC Completed. Switch yard - Foundation PCC completed approach bridge and intake pipe line excavation in progress |
No file Uploaded |
08-09-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
08-09-2021 |
Work in progress at ESR -01,ESR 04, ESR 06 , ESR 07,ESR 08 , ESR 10,ESR 11 & ESR 12 |
No file Uploaded |
08-09-2021 |
Clear water pipe line : Excavation and laying completed - 10 KM |
No file Uploaded |
08-09-2021 |
Distribution System : Completed 14.2 KM in Zone 4 & Zone 15 |
No file Uploaded |
08-09-2021 |
Staff quarters : Work in progress at CWR +PH -03 |
No file Uploaded |
08-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 3 beds PCC completed out of 6 Nos |
No file Uploaded |
08-09-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
08-09-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
07-09-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
07-09-2021 |
Clear water pipe line : Excavation and laying completed - 9.8 KM |
No file Uploaded |
07-09-2021 |
Distribution System : Completed 14 KM in Zone 4 & Zone 15 |
No file Uploaded |
07-09-2021 |
Staff quarters : Work in progress at CWR +PH -03 |
No file Uploaded |
07-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 3 beds PCC completed out of 6 Nos |
No file Uploaded |
07-09-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
07-09-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
06-09-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
06-09-2021 |
Clear water pipe line : Excavation and laying completed - 9.6 KM |
No file Uploaded |
06-09-2021 |
Distribution System : Completed 13.5 KM in Zone 14 & Zone 15 |
No file Uploaded |
06-09-2021 |
Staff quarters : Work in progress at CWR +PH -03 |
No file Uploaded |
06-09-2021 |
1) Aerator- Haft height structure completed 2 ) Raw water Channel ,Flash mixers - Haft height structure completed 3) Chemical House & Chlorine house up to lintel level completed 4) Clari flocculator Outer wall concrete completed - Inside PCC in progress 5) Filter beds Bottom raft completed and side walls up to plinth completed - Filter beds 3 beds PCC completed out of 6 Nos |
No file Uploaded |
06-09-2021 |
1) Work in progress at CWR-01,CWR 3 , CWR 04, CWR 5,CWR 6, CWR 8, CWR 10 & CWR 11 |
No file Uploaded |
06-09-2021 |
1) Work in progress at ESR -02,ESR -03, ESR -04, ESR -05, ESR -06, ESR -08, ESR -09, ESR -11, ESR 12 , ESR -13, ESR 14, ESR 15 , ESR 20, ESR 21, ESR 22, ESR 24 |
No file Uploaded |
01-09-2021 |
Intake well: PCC Completed. Switch yard , approach bridge and intake pipe line excavation in progress |
No file Uploaded |
01-09-2021 |
DI Pipe 800 mm Dia K9 pipes reached site around 5 km. 2. Forest department permissions awaited. 3) Excavation and laying of pipe line s Completed as on date 2.0 KM |
No file Uploaded |
01-09-2021 |
Clear water pipe line : Excavation and laying completed - 3.5 KM |
No file Uploaded |
01-09-2021 |
Distribution System : Completed 12 KM in Zone 4 & Zone 15 |
No file Uploaded |
01-09-2021 |
Staff quarters : Work in progress at CWR +PH -03 |
No file Uploaded |
01-09-2021 |
1) Aerator, Raw water Channel ,Flash mixers , Up to Plinth level completed -2) Chemical House & Chlorine house up to Roof slab completed 3) Clari flocculator Outer wall PCC completed - Reinforcement work in progress 4) Filter beds bottom raft completed. Side walls in progress |
No file Uploaded |